Cape Coral, FL Parking Rules: EV Charging (2026)
Key Facts
- Trigger size
- 200,000 sq. ft. gross floor area
- Base requirement
- 1 charging station
- Scaling rule
- +1 station per 20,000 sq. ft. beyond
- Adopted by
- Ordinance 66-23 (9-6-2023)
- Governing section
- LDC § 6.1.7.C
Summary
Large Cape Coral developments must install electric vehicle charging stations under Land Development Code Section 6.1.7.C. Any site of 200,000 square feet of gross floor area or more needs at least one charging station, with an additional station required for every extra 20,000 square feet of development beyond that first threshold.
C.Electric vehicle charging stations. Charging stations for electric vehicles shall be required for all development sites of 200,000 square feet of gross floor area or more. One charging station shall be required for the initial 200,000 square feet of development and an additional charging station shall be provided for each additional 20,000 square feet over that.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 38).
Full Breakdown
7, "Amount of required parking," folds electric vehicle charging into the City's off-street parking standards rather than treating it as a stand-alone article. Subsection C sets a size-based trigger: a development site reaches the charging-station requirement once its gross floor area hits 200,000 square feet. At that threshold the developer must provide one charging station, and the requirement scales upward from there, adding one more station for every additional 20,000 square feet of gross floor area above the initial 200,000-square-foot mark. Because the standard is measured against gross floor area rather than parking-space count, it applies across use types, from big-box retail and office parks to large multi-family projects, wherever the building program crosses the size threshold.
C, showing the City treats EV infrastructure as a large-development obligation rather than a universal one. Compliance is verified at the site-plan stage: Development Services checks the charging-station count against the gross-floor-area calculation before approving the plan, and the requirement was added to the code by Ordinance 66-23 on September 6, 2023, in the same amendment that revised the loading-facility and common-driveway standards elsewhere in Chapter 1. Smaller developments under the 200,000-square-foot floor face no mandatory charging-station count, though nothing in the code stops a developer from installing charging stations voluntarily as an amenity.
Violations & Fines
A site plan that omits the required electric vehicle charging stations does not meet Section 6.1.7.C and cannot receive Development Services approval. For a project already built without the required stations, the general Land Development Code violations clause in Section 1.6 applies, routing enforcement through the Chapter 2, Article 5 code enforcement procedures of the City Code of Ordinances and a possible special magistrate hearing.
Frequently Asked Questions
What size Cape Coral development triggers the EV charging station requirement?
How many EV charging stations does a large Cape Coral project need?
When did Cape Coral add its electric vehicle charging requirement?
Sources & Official References
Other rules in Cape Coral
Florida rules heatmap·Compare Cape Coral to another location·View the Florida parking rules overview