Broomfield, CO Sidewalk & Pedestrian Rules: Encroachment Permits (2026)
Key Facts
- Governing chapter
- Municipal Code Ch. 14-10
- Permit required for
- Construction, excavation, work in right-of-way
- Occupation application fee
- $500.00 nonrefundable
- Security threshold
- $2,000.00 construction cost
- Warranty period
- 2 years (1 year landscaping)
- Unpermitted excavation surcharge
- $250.00
- Enforcing official
- Director of Community Development
Summary
Broomfield requires anyone who wants to build, excavate, or place facilities in a public right-of-way, including sidewalks, alleys, and easements, to first obtain a permit from Community Development under Municipal Code Chapter 14-10. The permit process covers private users like utility companies, contractors, and property owners doing work that touches city-owned right-of-way, with fees, inspections, and a warranty period attached.
No person except an employee or official of the city or a person exempted by contract with the city shall undertake or permit to be undertaken any construction, excavation, or work in the public rights-of-way without first obtaining a permit from the city as set forth in this chapter, except as provided in section 14-10-210, B.M.C. ... If the total construction cost of the proposed permit exceeds $2,000.00, a performance/warranty guarantee (security) will be required of the permittee in the form of a letter of credit or a cash deposit. No bonds will be accepted. ... If any person, firm, or corporation shall violate or cause the violation of any of the provisions of this chapter, they shall be guilty of a separate offense for each and every day or portion thereof during which a violation is committed, continues, or is permitted, and upon conviction of any such violation such person, firm, or corporation shall be punished as provided in chapter 1-12, B.M.C. for each such violation.
Full Breakdown
Broomfield's Use of Public Rights-of-Way chapter (14-10) requires any person other than a city employee to obtain a permit before undertaking construction, excavation, or work in a public right-of-way, per Section 14-10-040. The application, filed with the director of community development under Section 14-10-050, must include the applicant's contact information, a description of the work, a storage plan, hours of work, and payment of fees set by council resolution; a supplementary application is required if the work area or timeline expands beyond what was approved.
Separately, anyone wanting ongoing occupation of the right-of-way, such as a utility placing permanent facilities, must obtain permission from the city council under Section 14-10-060, which requires a nonrefundable $500.00 application fee and triggers a public hearing held within 45 days of a complete application. Under Section 14-10-080, any permit for construction exceeding $2,000.00 in cost requires a letter of credit or cash deposit as a performance and warranty guarantee, held for two years; no bonds are accepted, and the guarantee is waived for residential utility and sidewalk repairs.
Section 14-10-100 requires at least three city inspections, including a pre-construction inspection and a final inspection roughly 30 days before the two-year warranty period expires. Emergency repairs may proceed without a permit under Section 14-10-210, but the responsible party must apply for one within three working days. A permit may be revoked by the director for violating any permit condition or ordinance under Section 14-10-220, with revocations and stop-work orders appealable to the city manager within 30 days under Section 14-10-230.
Violations & Fines
Working in the right-of-way without a permit is a municipal offense under Section 14-10-240, punished under Chapter 1-12's general penalty provisions, with each day of a continuing violation counted as a separate offense. Section 14-10-040(E) adds a $250.00 surcharge on top of standard permit fees for anyone caught excavating without first obtaining the required permit, and work must stop immediately until a permit is issued. The director can also revoke an existing permit or issue a stop-work order for any violation of permit conditions.
Frequently Asked Questions
Who needs a right-of-way encroachment permit in Broomfield?
How much does it cost to occupy the right-of-way long-term?
What happens if I excavate without a permit first?
Can I appeal if my encroachment permit is revoked?
Sources & Official References
Other rules in Broomfield
Compare Broomfield to another location·View the Colorado sidewalk & pedestrian rules overview