Key Facts

Base ROW permit fee
$200 application fee
Working without a permit
3x the original permit fee
Sidewalk/curb work
$50 per 50 linear ft, $150 min
Driveway approach ≤24 ft
$100 flat fee
Restoration bond
110% of value of work
Current ordinance date
Ord. No. 2025-09-28 (9-9-25)

Summary

Any private work in a Homestead public right-of-way, from a new sidewalk to a driveway approach, needs a Public Works ROW permit starting at $200; starting work without one triples the permit fee under Sec. 7-6.

Sec. 24-6. - Right-of-way permit fees. (b)Right-of-way (ROW) permit application and pre-construction inspection fees. a. ROW permit application* $200.00 d. Work start without a ROW permit - Fee equivalent to 3 x original permit fee *Includes administrative review, pre-construction meeting (mandatory), and pre-construction site assessment (e)Sidewalks, curb/gutter, concrete separators within the right-of-way (ROW) permit review fees. a. New sidewalk/repair-Sidewalk per 50 linear feet $50.00 per 50 l.f. or fraction thereof (minimum fee $150.00) (k)Inspection fees and fees for other services. a. Restoration bond (credit letter or cash bond) - Bond equivalent to 110% of the value of work, which shall be determined by the director of public works b. Inspection fee $75.00 Per hour with a minimum charge of two hours

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 87).

Full Breakdown

Sec. 24-6 of the City Code sets a full fee schedule for right-of-way (ROW) permits covering sidewalks, curbs, driveway approaches, street pavement, landscaping, and utility installation within city rights-of-way. The base ROW permit application fee is $200 and includes a mandatory pre-construction meeting and site assessment; a 90-day extension costs $50 if requested at least seven days before expiration. Sidewalk, curb and gutter, or median work is billed at $50 per 50 linear feet or fraction thereof, with a $150 minimum, while driveway approaches run $100 up to 24 feet wide and $120 each beyond that.

Applicants must post a restoration bond equal to 110 percent of the value of the work, as determined by the director of public works, and pay a $75-per-hour inspection fee with a two-hour minimum. If a first inspection fails, reinspection runs $100, then $150, then $200 plus $75 for each additional failed check after the third. The most recent version of this fee structure was adopted by Ord. No. 2025-09-28 on September 9, 2025. Related Sec. 24-17 separately makes it unlawful for anyone to extend or maintain a wire, rope, cable, or line over, across, or under a city street or public highway without first obtaining permission from the city council, a companion permission requirement for above- or below-grade encroachments that fall outside the standard construction permit fees.

Violations & Fines

Starting construction in the right-of-way before a permit issues triggers a fee equal to three times the original permit fee under Sec. 24-6(b). Failed inspections add reinspection charges on an escalating scale, $100 for the first, $150 for the second, and $200 plus $75 per additional check after the third, on top of the base $75-per-hour inspection fee, and the city can draw on the 110-percent restoration bond to cover any right-of-way left out of compliance.

Frequently Asked Questions

Do I need a permit to build a sidewalk in Homestead's right-of-way?
Yes. Sec. 24-6(e) charges $50 per 50 linear feet of new or repaired sidewalk, curb, gutter, or median, with a $150 minimum fee, and requires the standard ROW permit application and pre-construction review before work starts.
How much does a Homestead right-of-way permit cost?
The base ROW permit application is $200 and covers administrative review, a mandatory pre-construction meeting, and a site assessment. Specific work, like a $100 driveway approach or $50-per-50-feet sidewalk repair, is billed on top of that under Sec. 24-6.
What happens if I start work in Homestead's right-of-way without a permit?
Sec. 24-6(b) imposes a fee equal to three times the original ROW permit fee for starting work before the permit is issued, on top of any inspection and reinspection charges once the work is discovered.
Who reviews right-of-way permits in Homestead?
The Department of Public Works administers ROW permits under Sec. 24-6, requiring a mandatory pre-construction meeting and a restoration bond equal to 110 percent of the value of the work before construction in the right-of-way begins.

Sources & Official References

Other rules in Homestead

All Homestead rules

Florida rules heatmap·Compare Homestead to another location·View the Florida sidewalk & pedestrian rules overview

Get notified when Encroachment Permits in Homestead, FL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Encroachment Permits in Nearby Cities

How other cities in Miami-Dade County handle encroachment permits.

Hialeah, FL
Some Restrictions
Miami Beach, FL
Some Restrictions
Coral Gables, FL
Significant Restrictions
Doral, FL
Significant Restrictions
Miami, FL