Key Facts

Duty holder
Adjacent property owner
Time to start repair
30 days from notice
Time to finish repair
60 days from notice
City cost share
50 percent of city's cost
Admin surcharge if city does it
Up to 15 percent
Governing section
B.R.C. 1981 § 8-2-6

Summary

Boulder places the duty to keep abutting sidewalks in good repair on the adjacent property owner, not the city. Under Section 8-2-6, B.R.C. 1981, if the city manager finds a sidewalk substandard, the owner gets 30 days to start and 60 days to finish repairs, with the city sharing half the cost, or the city can do the work and bill the owner.

(a)No owner of property within the city shall fail to maintain the sidewalk on or adjacent to the owner's property in good repair and safe, unobstructed condition.(b)If the city manager finds that any portion of a sidewalk does not meet the standards prescribed in Section 8-2-17, ... the manager may require that the owner of the sidewalk or property adjacent to the sidewalk repair or replace the non-complying portion to bring it into conformity with city standards.(c)If the city manager determines to proceed under subsection (b) of this section, the manager shall notify the property owner of the duty to repair or replace, that such owner has thirty days from the date of the notice to commence such repair or replacement and has sixty days from the date of the notice to complete such repair or replacement, and that the city will share in the cost of the work as provided in subsection (e) of this section.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Municipal Code: Supplement 167 Update 3).

Full Breakdown

C. 1981, makes it a violation for any property owner in the city to fail to maintain the sidewalk on or adjacent to their property in good repair and in a safe, unobstructed condition. If the city manager finds that a sidewalk segment falls short of the construction standards set in Section 8-2-17, the manager can require the adjacent owner to repair or replace the non-complying portion. The manager's notice gives the owner 30 days from the date of the notice to begin the work and 60 days to complete it, though the manager may extend the deadline if weather would interfere.

As an alternative, the notice can offer an agreement under which the city completes the repair itself within 12 months and the owner pays their share within 30 days of completion. Under Subsection (e), the city splits the cost: it contributes an amount equal to 50 percent of what the city would have spent doing the work itself, subject to available appropriated funds. If an owner misses the deadline or does not sign a return agreement, the city manager can perform the repair or replacement directly and bill the owner for the cost, plus up to 15 percent for administrative overhead, under Subsection (d).

Unpaid charges, including any agreed installment, can be certified to the Boulder County Treasurer and collected the same way as delinquent property taxes, per Section 2-2-12. Notice is valid if mailed first class to the owner's address on the Boulder County Assessor's records.

Violations & Fines

Failing to maintain a sidewalk in good repair, or ignoring a city manager's repair notice under Section 8-2-6, lets the city perform the work itself and bill the property owner the full cost plus up to 15 percent for administration. Unpaid charges are certified to the Boulder County Treasurer and collected the same way as delinquent property taxes under Section 2-2-12, B.R.C. 1981.

Frequently Asked Questions

Who is responsible for fixing a cracked sidewalk in front of my Boulder home?
You are. Section 8-2-6(a), B.R.C. 1981, requires the owner of property adjacent to a sidewalk to keep it in good repair and in a safe, unobstructed condition. The city does not automatically fix sidewalks; it steps in only after finding a segment substandard and notifying the owner.
How long do I have to fix a sidewalk after the city notifies me?
Thirty days to begin the work and sixty days to complete it, both measured from the date of the notice, under Section 8-2-6(c). The city manager can extend either deadline if winter weather would interfere with the repair.
Will the city help pay for the sidewalk repair?
Yes, if the city manager proceeds under Section 8-2-6(b) and (e). Boulder contributes an amount equal to 50 percent of what the repair would have cost the city to perform itself, subject to available funding, and the manager can offer an agreement where the city does the work and the owner pays their share within 30 days of completion.
What happens if I ignore the repair notice?
The city manager can perform the repair or replacement directly and bill you for the full cost plus up to 15 percent for administrative overhead, under Section 8-2-6(d). If you don't pay, the charge is certified to the Boulder County Treasurer and collected the same way as delinquent property taxes.

Sources & Official References

Other rules in Boulder

All Boulder rules

Compare Boulder to another location·View the Colorado sidewalk & pedestrian rules overview

Get notified when Sidewalk Repair in Boulder, CO changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Sidewalk Repair in Nearby Cities

How other cities in Boulder County handle sidewalk repair.

Longmont, CO
Some Restrictions