Skip to main content
CityRuleLookup

Clarkstown, NY Solar Energy: Expedited Solar Permitting (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Program
Unified statewide solar permit, § 247-9
Permit type
Combined building + electrical permit
Required checklist
Unified Solar Permit Eligibility Checklist
Plan sets required
Three sets: site plan, electrical diagram, specs
Other chapters still apply
§ 247-10: Ch. 270 and Ch. 249A not excused

Summary

Clarkstown runs a Solar Panel Fast-Track Program under Town Code § 247-9 that issues a combined building and electrical permit for grid-tied residential PV systems using New York State's unified solar permit form and checklist.

The expedited solar permitting process uses a unified permit across municipalities in New York State. A combined building and electrical permit for a grid-tied photovoltaic (PV) system will be issued pending proper completion of forms, submission of approved plans and approval by the municipality. All applicants must submit: A. Unified Solar Permit Eligibility Checklist (annexed as Attachment 1). B. Three sets of plans that include: (1) Site plan showing location of major components of solar system and other equipment on roof or legal accessory building. ... (2) One-line or three-line electrical diagram. ... (3) Specification sheets for all manufactured components. If these sheets are available electronically, a web address will be accepted in place of an attachment, at the discretion of the Building Inspector.

Full Breakdown

Section 247-9, "Solar Panel Fast-Track Program," tells applicants that "the expedited solar permitting process uses a unified permit across municipalities in New York State," and that a single combined building and electrical permit for a grid-tied photovoltaic system issues once the forms are properly completed, plans are submitted and the municipality signs off. Every applicant must submit the Unified Solar Permit Eligibility Checklist, annexed to the chapter as Attachment 1, along with three sets of plans. Those plans must include a site plan showing the array, existing electrical service location, utility meter, inverter location, system orientation, tilt angle, and any access pathways that need to comply with the New York State Fire Code; a one-line or three-line electrical diagram (the same one used for a NYSERDA incentive application or a utility interconnection agreement satisfies this); and specification sheets for every manufactured component, which the Building Inspector may accept as a web link instead of a paper attachment.

All diagrams and plans must also state the project address, section/block/lot, the owner's contact information, the plan preparer's contact information, and the system's DC capacity in kW. Section 247-10 makes clear the fast-track program does not excuse compliance with other applicable chapters, including Chapter 270 and the Chapter 249A stormwater rules, so a project that also disturbs 10,000 square feet or more of land still needs a separate stormwater pollution prevention plan even while moving through the expedited track.

Violations & Fines

A fast-tracked system installed without completing the Unified Solar Permit Eligibility Checklist, submitting the required plan sets, or clearing any other chapter the project triggers (such as the Chapter 249A stormwater rules cross-referenced in § 247-10) falls under the general Chapter 247 penalty in § 247-11: a fine up to $1,000 and/or imprisonment up to one year, with each day of continued noncompliance a separate offense.

Frequently Asked Questions

What is Clarkstown's Solar Fast-Track Program?
It is the unified, statewide expedited solar permitting process adopted in § 247-9, under which a single combined building and electrical permit is issued for a grid-tied residential PV system once the Unified Solar Permit Eligibility Checklist and three sets of plans are submitted and approved.
What plans does the fast-track application need?
A site plan showing the array, meter, inverter and orientation; a one-line or three-line electrical diagram (a NYSERDA or utility interconnection diagram works); and manufacturer specification sheets, which the Building Inspector may accept as a web address instead of paper copies.
Does the fast-track program skip stormwater review?
No. Section 247-10 states that nothing in Chapter 247 precludes compliance with other applicable statutes, expressly naming Chapter 270 and Chapter 249A, so a fast-tracked project that disturbs enough land still needs its own stormwater sign-off.

Sources & Official References

Other rules in Clarkstown

All Clarkstown rules

New York rules heatmap·Compare Clarkstown to another location·View the New York solar energy overview

Get notified when Expedited Solar Permitting in Clarkstown, NY changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.