Highland, CA Solar Energy: Expedited Solar Permitting (2026)

Light Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Over-the-counter permit
Issued the same day for complete applications
Electronic applications
Permit issued within one to three business days
Inspections required
Only one for eligible systems
Inspection scheduling
Best efforts within two business days, two-hour window
Scope of review
Local, state, and federal health and safety requirements
Fees
Set by resolution of the Highland City Council

Summary

In the City of Highland, California, a complete application for a small residential rooftop solar energy system gets its building permit the same day at the counter or within one to three business days when filed electronically. Chapter 15.80 of the Highland Municipal Code limits review to health and safety and requires only one inspection.

§ 15.80.030. Permit application review. A. An application that satisfies the information requirements in the checklist(s) and standard plan(s) shall be deemed complete. B. If an application is deemed incomplete, a written correction notice detailing all deficiencies in the application and any additional information or documentation required to be eligible for expedited permit issuance shall be sent to the applicant for resubmission. C. The building official shall issue a building permit for any complete application that meets the requirements of the approved checklist(s) and standard plan(s) as follows: the same day for over-the-counter applications, within one to three business days for electronic applications, or as soon thereafter as may be practicable. Review of the application shall be limited to the building official's review of whether the application meets local, state, and federal health and safety requirements. D. Any condition imposed on an application shall be designed to mitigate the specific, adverse impact upon health and safety at the lowest possible cost.

Full Breakdown

Chapter 15.80 of the Highland Municipal Code, adopted by Ordinance 401 in 2015, sets the expedited track for small residential rooftop solar systems in the City of Highland, San Bernardino County. Section 15.80.010 does not write its own definitions. It borrows the meaning of "electronic submittal" and "small residential rooftop solar energy system" from the Solar Rights Act, Government Code Section 65850.5(j)(2) and (j)(3).

Under § 15.80.020 the city must adopt standard plans and a checklist of every requirement a system has to meet to qualify. Those documents must substantially conform to the California Solar Permitting Guidebook adopted by the Governor's Office of Planning and Research, and everything needed to apply must be posted on the city website. Electronic applications go through the method the building official specifies, and an applicant's electronic signature is accepted in place of a wet signature.

Section 15.80.030 governs the review itself. An application that satisfies the checklist and standard plan is deemed complete. An incomplete application draws a written correction notice that lists all deficiencies and any added information needed for expedited issuance. The building official then issues the permit the same day for over-the-counter applications or within one to three business days for electronic applications. Review is confined to whether the application meets local, state, and federal health and safety requirements, and any condition must be designed to mitigate the specific, adverse impact upon health and safety at the lowest possible cost.

Section 15.80.040 allows inspection requests by electronic submittal and permits only one inspection for eligible systems. The building official uses best efforts to schedule it within two business days and to offer a two-hour window. A failed inspection is followed by another inspection that does not have to meet those timing rules. Under § 15.80.050, permit and inspection fees are set by resolution of the city council.

Violations & Fines

Chapter 15.80 contains no penalty clause of its own, because it binds the city's review timeline rather than the applicant. A defective filing produces a written correction notice and a resubmission. A system that fails inspection is followed by a further inspection, and the building official is not held to the two-business-day scheduling target for that follow-up visit.

Frequently Asked Questions

How fast does Highland issue a rooftop solar permit?
Under Highland Municipal Code § 15.80.030, the building official issues the permit the same day for a complete over-the-counter application and within one to three business days for a complete electronic application. The code adds the phrase "or as soon thereafter as may be practicable," so the stated windows are targets tied to a complete filing.
What happens if my Highland solar application is incomplete?
The city must send a written correction notice detailing all deficiencies and any additional information or documentation needed to qualify for expedited issuance. You then resubmit. An application that satisfies the information requirements in the city's checklist and standard plan is deemed complete, so the checklist on the city website is the test.
How many inspections does a small residential rooftop system get in Highland?
Section 15.80.040 requires and allows only one inspection by the building official for eligible systems. Requests can be filed electronically, and the building official uses best efforts to schedule the visit within two business days with a two-hour inspection window. If the system fails, a subsequent inspection is authorized.
Can Highland add conditions to a solar permit?
Any condition imposed on an application must be designed to mitigate the specific, adverse impact upon health and safety at the lowest possible cost. Review is limited to whether the application meets local, state, and federal health and safety requirements, so conditions unrelated to health and safety fall outside § 15.80.030.

Sources & Official References

Other rules in Highland

All Highland rules

California rules heatmap·Compare Highland to another location·View the California solar energy overview

Get notified when Expedited Solar Permitting in Highland, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Expedited Solar Permitting in Nearby Cities

How other cities in San Bernardino County handle expedited solar permitting.

Chino, CA
Light Restrictions
Fontana, CA
Light Restrictions
Rancho Cucamonga, CA
Light Restrictions
Ontario, CA
Light Restrictions
Rialto, CA
Some Restrictions