Key Facts

Review timeline
3 business days for a complete application
System size cap
10 kW AC / 30 kW thermal
Eligible buildings
Single or duplex family dwellings
Reviewing department
Building Department / Building and Safety Director
HOA approval
Cannot be required for permit issuance
Adopted
Ordinance 1885, 2015

Summary

Palm Springs must approve or reject a small residential rooftop solar permit within three business days once an application meets the city's checklist, under the AB 2188 expedited process in Chapter 8.100. The streamlined track covers systems up to 10 kilowatts AC or 30 kilowatts thermal on a single-family or duplex home.

The intent and purpose of this chapter is to adopt an expedited, streamlined solar permitting process that complies with AB 2188 (Chapter 521, Statutes 2014, California Government Code Section 65850.5) to achieve timely and costeffective installations of small residential rooftop solar energy systems. ... "Small residential rooftop solar energy system" means all of the following: ... A solar energy system that is not larger than 10 kilowatts alternating current nameplate rating or 30 kilowatts thermal ... For an application for a small residential rooftop solar energy system that meets the requirements of the City's checklist, the Building Department shall issue a building permit or other non-discretionary permit or authorization within three business days.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4923139; v14 updated 2026-06-24).

Full Breakdown

5) by creating a nondiscretionary, expedited permitting track for small residential rooftop solar. A qualifying system cannot exceed 10 kilowatts of alternating-current nameplate rating or 30 kilowatts thermal, must be installed on a single or duplex family dwelling, must conform to all applicable state fire, structural and electrical codes, and cannot exceed the city's maximum legal building height. 060 is limited to whether the application meets local, state and federal code requirements, nothing more discretionary than that. A complete application that satisfies the checklist gets a building permit or other non-discretionary authorization within three business days; an incomplete one draws a written correction notice detailing every deficiency so the applicant can resubmit.

340(b). 55 and 66015 and Health and Safety Code Section 17951, all of which cap what the city can charge relative to its actual permitting cost. 060(G) bars the city from conditioning permit approval on sign-off from a homeowners' association, so an HOA objection alone cannot block or delay the three-day review clock.

Violations & Fines

Installing a system without the required permit exposes the owner to standard citywide code-enforcement remedies, including stop-work orders and the general infraction and misdemeanor penalties in Sections 1.01.155 and 1.01.160, since Chapter 8.100 itself sets no separate fine; the chapter's own teeth are procedural, requiring correction notices and written findings before any permit can be denied.

Frequently Asked Questions

How fast does Palm Springs have to issue my solar permit?
Three business days from a complete application, under Section 8.100.060(B), as long as the submission meets the Building Department's published checklist. An incomplete application instead gets a written correction notice listing every missing item so it can be resubmitted for the same expedited clock.
Can my HOA block my rooftop solar permit in Palm Springs?
No. Section 8.100.060(G) bars the city from conditioning approval of a solar application on sign-off from an association as defined in California Civil Code Section 4080, so an HOA's disapproval cannot be used to withhold or delay the building permit itself.
What size solar system qualifies for the expedited process?
Up to 10 kilowatts of alternating-current nameplate rating, or 30 kilowatts thermal, installed on a single or duplex family home and not exceeding the city's maximum legal building height. Larger systems, or those on other property types, fall outside Chapter 8.100 and follow standard discretionary permitting instead.

Sources & Official References

Other rules in Palm Springs

All Palm Springs rules

California rules heatmap·Compare Palm Springs to another location·View the California solar energy overview

Get notified when Expedited Solar Permitting in Palm Springs, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Expedited Solar Permitting in Nearby Cities

How other cities in Riverside County handle expedited solar permitting.

Menifee, CA
Light Restrictions
Temecula, CA
Light Restrictions
Corona, CA
Some Restrictions
Murrieta, CA
Some Restrictions
Riverside, CA
Few Restrictions
Moreno Valley, CA
Few Restrictions