Berwyn, IL Solar Energy: Panel Permits (2026)
Key Facts
- Permit designation
- "B" (building permit) in all ten districts
- Roof-mounted districts
- All zoning districts
- Roof-mounted height
- Five feet above the structure's overall height
- Front-facing roof face
- Not allowed if parallel to the front lot line
- Ground-mounted districts
- C-1, C-2, C-3, C-4, I and P only
- Electrical standard
- Chapter 1424 (City of Chicago Electrical Code)
Summary
In the City of Berwyn, Illinois, a solar energy collection system is an accessory structure marked "B" in every district, so it needs a building permit. Roof-mounted panels are allowed in all districts, but ground-mounted systems are limited to the C-1, C-2, C-3, C-4, I and P Districts under § 1244.04(C)(12).
(12) Solar energy collection system. Solar energy collection systems may be roof-mounted or ground-mounted in accordance with the following standards and those of Chapter 1424 (City of Chicago Electrical Code). (a) Roof-mounted system. Roof-mounted systems shall adhere to the following. 1. Districts. Roof-mounted systems are allowed in all zoning districts. 2. Location. A roof-mounted system shall not be located on a roof face that runs parallel to and faces the front lot line. 3. Height. The maximum height of a roof-mounted system shall be five feet above the overall height of the principal or accessory structure to which the system is attached. 4. Angle. A roof-mounted system must be mounted at the same angle as or flush with the roof of the structure when visible from the street, excluding alleys. (b) Ground-mounted system. Ground-mounted systems shall adhere to the following. 1. Districts. Ground-mounted systems are allowed in the C-1, C-2, C-3, C-4, I, and P Districts.
Full Breakdown
Table 1244.04-A of the Berwyn Code of Ordinances marks Solar Energy Collection System with a "B" in all ten zoning districts of the City of Berwyn, Cook County, Illinois. Under § 1244.04(B)(2), a "B" means the structure requires a building permit in accordance with Chapter 1443. Section 1244.04(C)(12) then sets the standards the installation has to meet, along with those of Chapter 1424 (City of Chicago Electrical Code), which Berwyn adopts for the electrical side of the work.
For roof-mounted systems, the code allows them in all zoning districts, which includes R-1 through R-4. Three design rules apply. The system cannot sit on a roof face that runs parallel to and faces the front lot line. Its maximum height is five feet above the overall height of the principal or accessory structure it is attached to. And when the system is visible from the street, excluding alleys, it must be mounted at the same angle as the roof or flush with it. In practice, panels on the street-facing slope of a bungalow are out, and panels on the rear or side slopes are in.
Ground-mounted systems are far more limited. They are allowed only in the C-1, C-2, C-3, C-4, I and P Districts, in the interior side and rear yards, up to the height limit of the applicable zoning district, and they have to be screened from view of the street by building or landscape screening under § 1250.05(A). Because the ground-mount district list leaves out R-1, R-2, R-3 and R-4, a backyard ground array is not on the residential menu.
The application goes to the Building Director under § 1443.01, with fees under Chapter 1444. Section 1444.02 charges an additional fee, and doubles the permit fee, when permit-required work starts before the permit issues.
Violations & Fines
The Zoning Administrator enforces the solar standards under § 1240.06. Violators are fined under the Municipal Code, each day is a separate offense, and the general penalty in § 202.99 is up to $2,000 per violation. Starting installation before the permit issues also triggers the § 1444.02 additional fee of $500 plus a doubled permit fee, for non-fence work.
Frequently Asked Questions
Do I need a permit for rooftop solar panels in Berwyn?
Can panels face the street on my Berwyn house?
How high can roof-mounted solar panels stand?
Can I install a ground-mounted solar array in my Berwyn backyard?
Sources & Official References
Other rules in Berwyn
Compare Berwyn to another location·View the Illinois solar energy overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Panel Permits in Nearby Cities
How other cities in Cook County handle panel permits.