Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit required
Yes, for all solar equipment, Sec. 18-49.1
Wind load standard
Racking must withstand 90 mph wind load
Contractor requirement
Louisiana-licensed electrical and solar contractor
Electrical standard
Current NFPA 70 National Electrical Code
Exemption
Nonhabitable structures like solar trellises exempt

Summary

Bossier City requires a building permit before installing any solar equipment under section 18-49.1. Applicants submit a structural engineer's analysis showing the roof or racking can handle a 90 mph wind load, an electrical riser diagram, and proof of a Louisiana-licensed electrical and solar contractor, with panels wired to current National Electrical Code standards.

A building permit is required for installing solar equipment. To obtain a solar permit the following is required: ... Submit structural engineer's analysis indicating roof is capable of supporting the load of equipment and the mounting/racking system will withstand a 90 miles per hour wind load. Include manufacturer's calculation for manufactured system. ... Solar permits require a LA licensed electrical and solar contractor. ... Note on plans that PV equipment shall be installed in accordance with current adopted edition of NFPA 70 (National Electric Code).

Full Breakdown

Section 18-49.1 of the Bossier City Code requires a building permit before installing solar equipment and lists what the application packet must contain. Applicants submit two complete sets of plans demonstrating every requirement: a structural engineer's analysis showing the roof can support the equipment's load and that the mounting or racking system will withstand a 90-mile-per-hour wind load, including the manufacturer's calculations for a manufactured system; a site plan, roof plan, and elevation and mounting details for the panel location, whether roof- or ground-mounted; an electrical riser diagram showing wire size and type, grounding, overcurrent protection rating, and disconnects; and, for solar hot water systems, a plumbing plan covering pipe size and type, exchange tank and backup water heater location, the pump, and whether the heat exchanger coil directly contacts potable water.

The application must also show adequate fire department access, pathways, and ventilation, and installation must be performed by a Louisiana-licensed electrical and solar contractor. Applicants submit a cut sheet and listing for the inverter, and plans must note that the photovoltaic equipment will be installed under the current adopted edition of NFPA 70, the National Electrical Code. Section 18-49.7 exempts nonhabitable structures such as parking shade structures and solar trellises from these requirements, while section 18-49.8 requires ground-mounted, freestanding arrays to meet all the same requirements.

Violations & Fines

Installing solar equipment without the section 18-49.1 permit and its required structural, electrical, and plumbing plans is treated as unpermitted building work under section 18-47: a misdemeanor punishable by a fine up to $500.00, up to 60 days in jail, or both. Starting installation before the permit issues also doubles the permit fee and adds a $500.00 penalty under section 18-40(b).

Frequently Asked Questions

Do I need a permit to install solar panels in Bossier City?
Yes. Section 18-49.1 requires a building permit before installing any solar equipment, roof- or ground-mounted, and lists the structural, electrical, and (for solar water heating) plumbing plans the application must include.
What wind load do Bossier City solar mounts have to meet?
Section 18-49.1 requires a structural engineer's analysis showing the roof can carry the equipment's load and that the mounting or racking system will withstand a 90-mile-per-hour wind load, with manufacturer's calculations submitted for a manufactured racking system.
Who can install a solar system in Bossier City?
Section 18-49.1 requires the work to be performed by a Louisiana-licensed electrical and solar contractor, and the plans must note that the photovoltaic equipment will be installed under the current adopted edition of NFPA 70, the National Electrical Code.

Sources & Official References

Other rules in Bossier City

All Bossier City rules

Compare Bossier City to another location·View the Louisiana solar energy overview

Get notified when Panel Permits in Bossier City, LA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.