Colorado Springs, CO Solar Energy: Panel Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit trigger
Install or modify a solar PV system
Exempt buildings
Group R-3 / IRC-built homes
Issuing office
Fire Prevention Bureau (Fire Code Official)
Maintenance
Routine maintenance is not a 'modification'
Ground-mount siting
Side/rear yards in most residential zones
General penalty
Up to $2,500 fine / 189 days jail

Summary

Installing or modifying a solar photovoltaic system in Colorado Springs requires a construction permit under the city's amended fire code, issued through the Fire Prevention Bureau before work begins. Group R-3 structures and homes built to the International Residential Code, which covers nearly every single-family house, are specifically carved out of this permit requirement.

105.6.20 Solar photovoltaic power systems. A construction permit is required to install or modify solar photovoltaic power systems. Maintenance performed in accordance with this Code is not considered to be a modification and does not require a permit. Exception: Group R-3 Structures and Structures designed and constructed in accordance with the International Residential Code.

Source: City of ArapahoeView official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2026 S-21: Code current through: Ord. 26-23, passed June 9, 2026).

Full Breakdown

20 states plainly that a construction permit is required to install or modify a solar photovoltaic power system. Routine maintenance performed in accordance with the Fire Code does not count as a modification and needs no permit. The section then carves out an exception for Group R-3 structures and any structure designed and constructed under the International Residential Code: the classification that covers the overwhelming majority of single-family homes in the city, so most homeowner rooftop installs never trigger this particular permit even though a contractor may still need separate building or electrical permits.

O (Solar Collector, Accessory): a roof-mounted collector may sit on a principal or accessory structure, and if it isn't flush with the roof the applicant must minimize its visibility from a public street, park, or green space without cutting its efficiency. Ground-based collectors in residential zone districts, other than the A zone, belong in side or rear yards without street frontage unless the only spot on the lot where the panels can function efficiently is a front yard or street-facing side yard. Both provisions were most recently touched by Ord. 23-03, with the fire code chapter last amended by Ord. 18-50 and Ord. 23-14.

Violations & Fines

Chapter 8.4 does not set its own fine schedule for a missing fire-code construction permit, so a violation falls to City Code § 1.1.201, the Code's general penalty clause. Municipal Court can impose a fine of up to $2,500, jail time of up to 189 days, probation, or a combination, per violation, for installing or modifying a covered photovoltaic system without the required permit.

Frequently Asked Questions

Do I need a permit to put solar panels on my house in Colorado Springs?
If your home is a Group R-3 structure or was built to the International Residential Code, true for essentially every single-family house, City Code § 8.4.105 (adopting IFC § 105.6.20) exempts you from the fire code construction permit otherwise required for solar photovoltaic installations. Separate electrical or building permits your contractor identifies may still apply.
Where can I place ground-mounted solar panels on my lot?
Under UDC § 7.3.304.O, ground-based solar collectors in residential zone districts other than the A zone belong in side or rear yards without street frontage, unless the only spot on the lot where the panels can function efficiently is a front yard or street-facing side yard.
What happens if a covered solar system is installed without the required fire code permit?
Chapter 8.4 doesn't list its own fine for this, so it falls under City Code § 1.1.201, the general penalty clause: a fine of up to $2,500, up to 189 days in jail, probation, or a combination, imposed by Municipal Court.

Sources & Official References

Other rules in Colorado Springs

All Colorado Springs rules

Compare Colorado Springs to another location·View the Colorado solar energy overview

Get notified when Panel Permits in Colorado Springs, CO changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.