Perth Amboy, NJ Solar Energy: Panel Permits (2026)

Light Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Solar panels, grounding grids, disconnect switch
$20 per unit (module), electrical schedule
Active solar system
$100, plumbing schedule
Electrical minimum fee
$75
Change of contractor or owner
$75 on an issued permit
Enforcing agency
Office of Construction and Fire Prevention

Summary

In the City of Perth Amboy, § 184-2 charges $20 per unit (module) for solar panels, grounding grids and disconnect switches on the electrical fee schedule, and $100 for an active solar system on the plumbing schedule. The Office of Construction and Fire Prevention administers the Uniform Construction Code.

(14) Active solar system $100 ... (7) Solar panels, grounding grids, disconnect switch etc., per unit (module) $20 (8) Branch circuits $35 ... (13) Administrative fees as follows: (a) For review of any amendments for change to a plan that has already been released, there shall be an additional fee of $75 per hour, minimum of one hour (b) Change of contractor or change of owner on an issued permit shall require an additional fee of $75

Full Breakdown

Solar work in the City of Perth Amboy is priced in two places in § 184-2 of the City Code, the Uniform Construction Code fee schedule. On the electrical schedule, item (7) reads "Solar panels, grounding grids, disconnect switch etc., per unit (module)" at $20. The charge follows the module count. Branch circuits, the next item, are $35, and the electrical minimum fee is $75. On the plumbing schedule, item (14) reads "Active solar system" at $100.

Section 184-2 prints fees rather than application steps. The enforcing body is the Office of Construction and Fire Prevention, which § 184-1 creates. It consists of the Construction Official as chief administrator and Building, Plumbing, Electrical, Elevator and Fire Protection Subcode Officials. Section 184-1 B lets the city retain an on-site third-party inspection agency by contract in place of a particular subcode official, and § 184-2 B sets a private agency's charge at the uniform percentage bid of the state fee plus a forty percent (40%) administrative fee.

Changes after approval carry their own charges under § 184-2. Reviewing an amendment to a plan that has already been released costs an additional $75 per hour, minimum of one hour, and changing the contractor or owner on an issued permit costs an additional $75. Other electrical work requiring review and inspection is billed at $75 per hour with a one hour minimum. Section 184-2 D also provides for a state training surcharge based on the volume of new construction.

Violations & Fines

Section 184-4 says violations of Chapter 184 shall be punishable pursuant to N.J.A.C. 5:23-1 et seq., so the chapter prints no fine figure of its own for unpermitted solar work. The fee items above are the only solar-specific figures in the schedule.

Frequently Asked Questions

How much is a solar panel permit fee in Perth Amboy?
The electrical fee schedule in § 184-2 of the Perth Amboy City Code prices solar panels, grounding grids and disconnect switches at $20 per unit (module). The schedule prices each module, so the charge follows the module count. The electrical minimum fee is $75.
Is there a separate fee for an active solar system?
Yes. The plumbing fee schedule in § 184-2 lists item (14), Active solar system, at $100. That is a separate line from the electrical schedule's per-module charge for solar panels, grounding grids and disconnect switches, so both schedules carry solar figures.
Who administers solar permits in Perth Amboy?
The Office of Construction and Fire Prevention, established by § 184-1, administers the New Jersey Uniform Construction Code for the City of Perth Amboy. The Construction Official is its chief administrator, and it includes an Electrical Subcode Official and a Plumbing Subcode Official, the two subcodes that carry solar fee lines.
What happens if I change contractors after the permit is issued?
Section 184-2 prints an additional $75 fee for a change of contractor or change of owner on an issued permit. Reviewing an amendment to a plan that has already been released costs an additional $75 per hour, with a minimum of one hour.

Sources & Official References

Other rules in Perth Amboy

All Perth Amboy rules

Compare Perth Amboy to another location·View the New Jersey solar energy overview

Get notified when Panel Permits in Perth Amboy, NJ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.