ADU rules in Arcadia, CA, also called accessory dwelling unit regulations or granny flat ordinances, cover setbacks, owner-occupancy, parking, and permit requirements.

Key Facts

Review type
Ministerial, no discretionary review or hearing
Decision deadline
60 days from a completed application
Detached ADU height
16 feet; 18 feet near major transit; 20 feet for roof pitch
Building-permit-only detached ADU
Four-foot side and rear setbacks, 800 square feet or smaller
ADU permit size cap
850 square feet studio/one-bedroom; 1,000 square feet two-plus bedrooms
Front setback (ADU permit)
25 feet
Section
Arcadia Municipal Code § 9102.01.080

Summary

In the City of Arcadia, California, an accessory dwelling unit is approved ministerially, without discretionary review or a hearing, under Arcadia Municipal Code § 9102.01.080. The city must approve or deny a completed application within 60 days. A detached ADU is capped at 16 feet in height, and a building-permit-only detached ADU needs side and rear setbacks of at least four feet.

A.Purpose. ... The purpose of this section is to allow and regulate accessory dwelling units (ADUs) and junior accessory dwelling units (JADUs) in compliance with Chapter 13 of Division 1 of Title 7 of the California Government Code. ... 3.Process and Timing. A.An ADU permit is considered and approved ministerially, without discretionary review or a hearing.B.The city must approve or deny an application to create an ADU or JADU within 60 days from the date that the city receives a completed application. ... 2.Height. ... A.Except as otherwise provided by subsections (E)(2)(B) and (E)(2)(C) below, a detached ADU created on a lot with an existing or proposed single family or multifamily dwelling unit may not exceed 16 feet in height.

Full Breakdown

Section 9102.01.080 of the Arcadia Development Code regulates both accessory dwelling units (ADUs) and junior accessory dwelling units (JADUs). Four scenarios need only a building permit. On a single-family lot, one converted ADU and one JADU are allowed inside existing or proposed living space, or inside an existing accessory structure plus up to 150 additional square feet for ingress and egress. A limited detached new-construction ADU on a single-family lot needs side and rear setbacks of at least four feet and a total floor area of 800 square feet or smaller. On a multifamily lot, converted ADUs in storage rooms, boiler rooms, passageways, attics, basements or garages are allowed up to 25 percent of the existing units, with at least one always allowed. A proposed multifamily building can add two detached ADUs, and an existing one up to eight, but never more than the number of primary dwelling units on the lot.

Everything else needs a building permit and an ADU permit. Those ADUs are capped at 850 square feet for a studio or one-bedroom and 1,000 square feet for two or more bedrooms, and an attached ADU is limited to 50 percent of the primary dwelling's floor area. No ADU may push the lot's floor area ratio above 45 percent, and the city cannot force any ADU below 800 square feet. Setbacks are four feet on the sides and rear and 25 feet in front. Lot coverage tops out at 45 percent for a one-story primary dwelling and 35 percent for a two-story one, and open space cannot fall below 50 percent.

Detached ADUs stop at 16 feet. The limit rises to 18 feet within one-half mile walking distance of a major transit stop or high quality transit corridor, and to 20 feet when needed to match the primary roof pitch. Attached ADUs may reach 25 feet or the zone limit, whichever is lower, and never more than two stories. Fire sprinklers are required in the ADU only when the primary residence must have them. If the city denies an application, it must send a list of every deficient item within the same 60-day window.

Violations & Fines

A use or structure that breaks the Development Code is declared a violation and a public nuisance under § 9108.15.070, and a violator is guilty of a misdemeanor punishable under Municipal Code Section 1200. City Code Services Staff start enforcement with a written Notice of Violation. Willful violations carry a civil penalty under the Fee Schedule for each day the violation continues. For a JADU that breaks its recorded deed restriction, the city can seek an injunction or abatement of the illegal unit.

Frequently Asked Questions

How long does the City of Arcadia have to decide an ADU application?
The city must approve or deny a completed ADU or JADU application within 60 days. If it misses that deadline, the application is deemed approved unless the applicant asked for a delay. When the ADU is filed together with a new single-family or multifamily dwelling, the city can wait to act on the ADU until it acts on the main dwelling.
How tall can a detached ADU be in the City of Arcadia, California?
A detached ADU cannot exceed 16 feet in height. It can reach 18 feet within one-half mile walking distance of a major transit stop or high quality transit corridor, and up to two more feet, for a maximum of 20 feet, if needed to match the roof pitch of the primary dwelling. Height is measured from existing legal grade or the lowest floor, whichever is lower, to the peak.
Does an Arcadia ADU need a hearing before the Planning Commission?
No. Section 9102.01.080 says an ADU permit is considered and approved ministerially, without discretionary review or a hearing. The city can charge a processing fee, which the director of community development sets and the city council approves by resolution. A demolition permit for a detached garage being replaced with an ADU is reviewed and issued together with the ADU application.
What setbacks apply to a new detached ADU in Arcadia?
A detached new-construction ADU on a single-family lot that qualifies for the building-permit-only track needs side and rear yard setbacks of at least four feet and a total floor area of 800 square feet or smaller. An ADU that needs an ADU permit must keep four-foot side and rear setbacks and a 25-foot front setback, and no setback applies if it replaces an existing structure in the same location and dimensions.

Sources & Official References

Other rules in Arcadia

All Arcadia rules

How Arcadia compares: Easiest Cities to Build an ADU·California rules heatmap·Compare Arcadia to another location·View the California accessory structures overview

Get notified when ADU Rules in Arcadia, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

ADU Rules in Nearby Cities

How other cities in Los Angeles County handle adu rules.

Burbank, CA
Some Restrictions
Carson, CA
Some Restrictions
Compton, CA
Some Restrictions
Downey, CA
Some Restrictions
El Monte, CA
Some Restrictions
Glendale, CA
Some Restrictions
Inglewood, CA
Some Restrictions
Lakewood, CA
Some Restrictions