Ankeny, IA Building Safety: Building Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Base code
2024 IBC, locally amended
No longer exempt
Fences ≤7 ft, sidewalks, small sheds, pools
Permit term
12 months from issuance
Fee waiver
Federal/state/county/city work, not abatement
Consequence of skipped inspection
Permit revocation, future permits barred

Summary

Under the Ankeny Building Code (IBC 2024 as locally amended), a permit is required for construction work unless it falls within an exemption, and Section 175.11 narrows the standard IBC exemption list, striking automatic exemptions for small detached structures, fences, sidewalks, driveways, prefabricated pools and shade cloth structures.

Section 105.2 Work Exempt From Permit. ... Section 105.2 Building - Item #1 Detached structures not exceeding 120 sq. ft. Delete Section 105.2 Building - Item #2 Fences not over 7 feet high Delete Section 105.2 Building - Item #6 Sidewalks and driveways Delete Section 105.2 Building - Item #9 Prefabricated swimming pools Delete Section 105.2 Building - Item #10 Shade cloth structures Delete ... Exemption from permit requirements of this chapter shall not preclude requirements for permitting of plumbing, electrical and mechanical installations and systems or compliance with Ankeny Code of Ordinances.

Full Breakdown

Ankeny adopts the 2024 International Building Code wholesale in Section 175.02, then amends it chapter by chapter. Section 175.11 rewrites the model IBC's Section 105.2, Work Exempt From Permit, deleting the stock exemptions for detached structures under 120 square feet, fences not over 7 feet, sidewalks and driveways, prefabricated swimming pools, and shade cloth structures, meaning all of those now need a City permit in Ankeny even though the base IBC would not require one. It also replaces the swings and playground equipment exemption with language limited to exterior swings and playground equipment, and states that being exempt from a building permit never excuses required plumbing, electrical or mechanical permits or other compliance with the Ankeny Code of Ordinances.

Every issued permit expires twelve months from the date of issue under Section 175.12, unless the application carried a longer approved construction schedule, and work cannot continue past expiration until the owner or agent renews the permit and pays the renewal fee set by City Council resolution. Section 175.13 makes the permit holder responsible for scheduling required inspections and obtaining final approval; skipping that step revokes the permit. Section 175.15 waives permit fees for exempt federal, state, county or City of Ankeny work, but not for abatement work performed under City direction.

Violations & Fines

Working past a permit's twelve-month expiration, or failing to schedule and pass required inspections before covering the work, revokes the permit under Section 175.13 and is treated as working without a permit in violation of city ordinance; the code bars further permits to that person or company until outstanding violations are resolved, and offenses are also enforceable as municipal infractions under Chapter 4 (up to $750 first offense, $1,000 each repeat day).

Frequently Asked Questions

Do I need a permit for a small shed in Ankeny?
Yes. Section 175.11 struck the standard IBC exemption for detached structures under 120 square feet, so unlike many cities, Ankeny requires a building permit for small accessory structures. It also removed exemptions for fences up to 7 feet, sidewalks, driveways, prefabricated swimming pools and shade cloth structures.
How long is an Ankeny building permit good for?
Section 175.12 gives every permit a twelve-month expiration from the date of issue, unless the application includes a longer construction schedule approved by the Building Official. Once expired, no further work is allowed until the owner or agent renews the permit and pays the renewal fee set by City Council resolution.
What happens if I build without scheduling inspections?
Section 175.13 makes it the permit holder's job to schedule required inspections and get final approval before covering the work. Skipping that step revokes the permit, counts as working without a permit in violation of city ordinance, and can block the person or company from getting future permits until outstanding violations are resolved.

Sources & Official References

Other rules in Ankeny

All Ankeny rules

Compare Ankeny to another location·View the Iowa building safety overview

Get notified when Building Permits in Ankeny, IA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.