Key Facts

Special permits needed for
moving, razing, demolishing, mobile-home install
Fee doubles if
work starts before permit issued
Fee schedule set under
§§ 2-5, 31-6, 31-8
Permits never authorize
blocking public thoroughfare or easement
Adopted base code
Minnesota State Building Code, § 10-1
Enforced by
Construction Services building official

Summary

Moving a building across Duluth, razing one, or installing a mobile home all need a special permit under § 10-2 of the Duluth Legislative Code, and starting any permitted work before the city issues the permit doubles the fee. No permit ever authorizes blocking a public street, ground or easement to get the job done.

(b) Special permits and fees. Special permits shall be obtained and special fees paid in all cases for items included in the following schedule whether said items are installed in new buildings or in existing buildings ... Fees for the following shall be set in accordance with Section 31-6(a) of this Code: (1) Moving over public property any building which has an area of 1,000 square feet or less on the first floor; ... (4) Razing or demolishing any building or structure; (5) The installation of a mobile home; ... (e) When work for which a permit is required by this Code is started or proceeded with before said permit is obtained, the fee specified shall be doubled, but the payment of such double fee shall not relieve any persons from fully complying with the requirements of the State Building Code in the execution of the work, nor from any other standards or penalties prescribed by law; (f) No permit to erect, repair or alter any building or structure shall authorize the use of any part of any public thoroughfare, or other public ground or easement.

Full Breakdown

Duluth adopts the Minnesota State Building Code by reference under § 10-1, so building permit requirements generally flow from that state code, administered by a Minnesota-certified building official within the city's construction services division. Section 10-2 lays out the city's own fee and special-permit rules on top of that framework. Building permit fees are collected under the current fee schedule adopted per §§ 2-5, 31-6 and 31-8, and special permits with their own fees are required for a defined list of items whether they involve new or existing buildings: moving over public property a building of 1,000 square feet or less on the first floor, moving a larger building over public property, moving any building not on public property at all, razing or demolishing a building or structure, and installing a mobile home.

Special permits are also required for electrical wiring, plumbing, heating plants and fireplaces regulated by the State Building Code when not covered by the general construction permit. If work requiring a permit starts before the permit is obtained, § 10-2(e) doubles the fee, though paying double doesn't excuse full compliance with the State Building Code or any other standard or penalty the law allows. Finally, § 10-2(f) makes clear a building permit's scope is limited: no permit to erect, repair or alter a building authorizes using any part of a public thoroughfare, public ground or easement, so work that spills into the right-of-way needs its own separate permit.

Violations & Fines

Starting work that needs a permit before the city issues one doubles the required fee under § 10-2(e), and that penalty doesn't excuse the contractor from still meeting every State Building Code requirement or any other standard or penalty the law allows. Using a public street, ground or easement beyond what a permit actually authorizes is a separate violation under § 10-2(f).

Frequently Asked Questions

Do I need a permit to move a building in Duluth?
Yes. Section 10-2(b) requires a special permit and fee to move any building over public property, whether it's under or over 1,000 square feet on the first floor, and a separate permit even to move a building not on public property at all.
What happens if I start construction in Duluth without a permit?
Section 10-2(e) doubles the permit fee for any work started before the permit is obtained, and paying that doubled fee still doesn't excuse full compliance with the State Building Code or any other applicable standard or penalty.
Can a Duluth building permit let me block the sidewalk?
No. Section 10-2(f) says no permit to erect, repair or alter a building authorizes using any part of a public thoroughfare, public ground or easement, so a separate right-of-way permit is needed for that.

Sources & Official References

Other rules in Duluth

All Duluth rules

Compare Duluth to another location·View the Minnesota building safety overview

Get notified when Building Permits in Duluth, MN changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.