Key Facts

Permit required for
construction, alteration, repair, demolition, system changes
Shed exemption
under 200 sq ft residential, 120 sq ft commercial
Fence exemption
6 feet or under
Permit expiration
180 days without work starting
Governing section
Goodyear City Code § 9-1-1 (amending IBC § 105.1)

Summary

Goodyear requires a building permit before anyone builds, alters, repairs, moves, or demolishes a structure, or installs an electrical, gas, mechanical, or plumbing system covered by the code. A handful of small jobs, like sheds under 200 square feet or fences under 6 feet, are exempt, and unpermitted work still owes fees for the missed step.

[A] 105.1 Required. Any owner or authorized agent who intends to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, or to erect, install, enlarge, alter, repair, remove, convert or replace any electrical, gas, mechanical or plumbing system, the installation of which is regulated by this code, or to cause any such work to be done, shall first make application to the building official and obtain the required permit. Permits are non-transferable without authorization of the building official, and any change in occupancy, operation, tenancy or ownership shall require a new permit. ... [A] 109.1.1 Building Permit Fees. Building permit fees for new construction, buildings and additions are to be calculated based on the city user fee schedule adopted by council.

View official code

Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through Ordinance 26-1648, passed April 27, 2026).

Full Breakdown

1 to require that any owner or authorized agent who intends to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, or to erect, install, enlarge, alter, repair, remove, convert or replace any electrical, gas, mechanical or plumbing system, shall first make application to the building official and obtain the required permit. Permits are not transferable without the building official's authorization, and any change in occupancy, tenancy, or ownership triggers the need for a new one. 2 carves out specific exemptions: detached accessory structures like tool sheds and playhouses under 200 square feet on residential lots (120 square feet on commercial lots), fences no taller than 6 feet, and like-for-like residential re-roofing, among others.

1, which sets building permit fees for new construction, buildings and additions based on the city's user fee schedule adopted by City Council rather than a flat number printed in the code. 5 if the authorized work does not start within 180 days of issuance or is suspended for 180 days after starting, though the building official can grant one or more 180-day extensions in writing for justified cause. 4, on top of the standard permit fee.

Violations & Fines

Working without the required permit exposes an owner to the added fee under Section 109.4 on top of the normal permit and plan review fees, and to code enforcement action for building without authorization. A permit that lapses under Section 105.5's 180-day rule has to be renewed at a new fee set by the building official before work can resume.

Frequently Asked Questions

Do I need a permit to remodel my house in Goodyear?
Yes, for most work. Section 9-1-1's amended IBC Section 105.1 requires a permit before you construct, enlarge, alter, repair, or change the occupancy of a building, or install or replace an electrical, gas, mechanical, or plumbing system covered by the code.
What small projects don't need a Goodyear building permit?
The amended Section 105.2 exempts detached accessory structures like sheds and playhouses under 200 square feet on residential property (120 square feet on commercial property), fences 6 feet or shorter, and like-for-like residential re-roofing using the same material as the original.
How is my Goodyear building permit fee calculated?
Section 109.1.1 bases building permit fees for new construction, buildings, and additions on the city's user fee schedule as adopted by City Council rather than a flat number written into the code itself; the exact cost is set from your project's valuation under Section 109.3.
What happens if I start work before getting a permit?
Section 109.4 makes you pay an added fee on top of the standard permit fee for any work started before the required permit was issued, even if the work itself would ultimately have been approved, and the building official sets that added charge from the city's fee schedule.

Sources & Official References

Other rules in Goodyear

All Goodyear rules

Compare Goodyear to another location·View the Arizona building safety overview

Get notified when Building Permits in Goodyear, AZ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Permits in Nearby Cities

How other cities in Maricopa County handle building permits.

Chandler, AZ
Light Restrictions
Mesa, AZ
Some Restrictions
Gilbert, AZ
Some Restrictions
Glendale, AZ
Some Restrictions
Surprise, AZ
Some Restrictions
Scottsdale, AZ
Some Restrictions
Peoria, AZ
Some Restrictions
Tempe, AZ
Some Restrictions