Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Adopted code
2024 International Building Code
Enforcing agency
Building Safety Division
Fence permit exemption
Up to 7 feet high
Hoophouse exemption
Per A.R.S. § 9-469
No-permit work found
Triggers investigation fee, § 109.5
Violation penalty
Misdemeanor under § 9-16(b)
Appeal deadline
30 calendar days to City Court

Summary

Glendale requires a permit under the adopted 2024 International Building Code for nearly every construction, alteration, or repair project, enforced by the city's Building Safety Division. Glendale Code § 9-17 exempts only specific items from IBC Section 105.2, including fences 7 feet or under and agricultural hoophouses and polyhouses built under A.R.S. § 9-469. Anything else needs a permit before work starts.

2.Fences, other than swimming pool barriers and perimeter subdivision fences, not over 7 feet (2134 mm) high. ... 14.Hoophouses and polyhouses used exclusively for producing and storing live plants, constructed in accordance with A.R.S. § 9-469. Mechanical, plumbing and electrical systems constructed in these structures shall require the appropriate permits in accordance with this code.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 115).

Full Breakdown

1, as amended). § 9-469, though any mechanical, plumbing, or electrical work inside those structures still needs its own permit. Everything not on the exemption list, including additions, remodels, new electrical service, plumbing, and mechanical systems, requires a permit before work begins. Permit, plan review, and investigation fees are set by council resolution under the rewritten Section 109; valuation for fee purposes covers the total cost of all labor, materials, overhead and profit on the permitted work. 5 requires a special investigation before the city will issue one, and the investigation fee applies whether or not a permit is ultimately granted.

6 makes it unlawful to keep working after the city serves notice suspending or revoking a permit; a suspended permit can only resume on the building official's written authorization, and a revoked permit is canceled with its fee forfeited. Decisions of the building official can be appealed to Glendale City Court within 30 calendar days under Section 113, for a non-refundable fee set under Glendale Code § 2-3.

Violations & Fines

Working under a permit that has been suspended or revoked is unlawful once the city serves notice on the permit holder, owner, or person in charge of the work, and a revoked permit's fee is not refunded. Violating any provision of the adopted codes under Section 9-16 is a misdemeanor. Starting work before obtaining a required permit triggers a mandatory special investigation and an added investigation fee under Section 109.5, regardless of whether a permit is later issued.

Frequently Asked Questions

Does a backyard fence need a permit in Glendale?
No, if it is 7 feet or less and is not a swimming pool barrier or perimeter subdivision fence, under Glendale Code § 9-17 amending IBC Section 105.2. Taller fences, pool barriers, and subdivision perimeter fences still need a building permit from the Building Safety Division before installation.
What happens if I build without a permit first?
Section 109.5 requires the Building Safety Division to conduct a special investigation before it will issue a permit for work already started, and it collects an investigation fee on top of the regular permit fee whether or not a permit is later approved. Non-compliant work can also be cited as a misdemeanor under Section 9-16.
Can I appeal a Glendale building official's decision?
Yes. Section 113 lets you appeal any order, decision, or interpretation of the building official to Glendale City Court. The written appeal and its fee, set under Glendale Code § 2-3, must reach the Court and the building official within 30 calendar days of the decision; the fee is non-refundable.
Are greenhouse-type hoophouses exempt from Glendale's permit rules?
Hoophouses and polyhouses used only to grow and store live plants are exempt from a building permit if constructed under A.R.S. § 9-469, per item 14 added to IBC Section 105.2. Any mechanical, plumbing, or electrical systems installed inside them still require their own separate permits under the city's code.

Sources & Official References

Other rules in Glendale

All Glendale rules

Compare Glendale to another location·View the Arizona building safety overview

Get notified when Building Permits in Glendale, AZ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Permits in Nearby Cities

How other cities in Maricopa County handle building permits.

Chandler, AZ
Light Restrictions
Mesa, AZ
Some Restrictions
Gilbert, AZ
Some Restrictions
Surprise, AZ
Some Restrictions
Goodyear, AZ
Some Restrictions
Scottsdale, AZ
Some Restrictions
Peoria, AZ
Some Restrictions
Tempe, AZ
Some Restrictions