Key Facts

Permit required for
Erect, alter, enlarge, move, demolish, or new parking lots
Plans required
2 full sets: foundation, elevations, floor plans
Permit expires
Void after 4 months unstarted or 60 days idle
Completion deadline
24 months from permit issuance
No-permit penalty
$100 or double fee, capped at $2,000
Issuing office
Building Division / Building Inspector

Summary

In the City of Janesville, Sec. 10-10 requires a Building Division permit before anyone erects, alters, enlarges, moves or demolishes a building or structure, or builds a new parking lot. The Building Inspector must find full compliance with the Municipal Building Code before issuing it, and unpermitted work triggers added fees and a possible stop-work order.

(a)Permit required. No person, firm or corporation shall directly or indirectly erect or construct any building or structure nor add to, enlarge, improve, structurally alter, convert, extend, move, wreck, or demolish, any building or structure or cause the same to be done, without first having obtained a permit therefor from the Building Division as hereinafter provided. A permit from the Building Division shall also be required for the construction, reconstruction or expansion of an off-street parking lot, open storage lot or loading area as hereinafter provided. ... (5)The building permit shall become void unless operations are commenced within four months from the date thereof, or if the building or work authorized by such permit is suspended at any time after work is commenced, for a period of 60 days. (6)Before any work is commenced or recommenced after the permit has lapsed, a new permit shall be issued at the regular fee rate. In any event, the work required to construct any building shall be completed within 24 months from the date of issuance of the permit.

Full Breakdown

Sec. 10-10(a) bars any person, firm or corporation from directly or indirectly erecting, constructing, adding to, enlarging, improving, structurally altering, converting, extending, moving, wrecking or demolishing any building or structure in the City of Janesville without first obtaining a permit from the Building Division, and the same permit requirement reaches new, reconstructed or expanded off-street parking lots, open storage lots and loading areas. Applicants submit a written application with two complete sets of plans, specifications and a plot or survey, drawn to a scale of at least one-fourth inch per foot and showing water supply, sewer connections and drainage; residential plans must include a foundation plan, all elevations, all floor plans and complete construction details.

Buildings other than one- and two-family homes that exceed 50,000 cubic feet need plans sealed by a registered architect or engineer under Sec. 10-10(g). Under Sec. 10-10(k), the Building Inspector issues the permit once satisfied the proposed work complies with the Code, other City ordinances and Wisconsin law; the permit becomes void if work has not started within four months, or is suspended for 60 days, and construction must finish within 24 months of issuance or a new permit at the regular fee is required.

The Inspector may revoke a permit under Sec. 10-10(l) for code violations, dangerous construction, false statements in the application, or inadequate site supervision, posting a revocation placard on the property.

Violations & Fines

Working without a required permit under Sec. 10-13(a)(3) draws a penalty of $100 or double the applicable permit fee, whichever is more, up to a $2,000 cap, on top of the normal permit fee itself. Sec. 10-31 separately doubles fees for any work commenced before a permit issues. The Building Inspector can revoke an active permit and issue a stop-work order under Sec. 10-17 whenever approved plans are not followed, and continuing work after a stop-work order is posted is itself unlawful under Sec. 10-10(l).

Frequently Asked Questions

What work requires a building permit in Janesville?
Sec. 10-10(a) requires a Building Division permit before erecting, adding to, enlarging, structurally altering, converting, extending, moving, wrecking or demolishing any building or structure, and also before building, reconstructing or expanding an off-street parking lot, open storage lot or loading area.
How long is a Janesville building permit valid?
Under Sec. 10-10(k)(5), the permit becomes void if work has not begun within four months of issuance, or if it is suspended for 60 days at any point after starting. Sec. 10-10(k)(6) also requires the entire job to finish within 24 months of issuance, or a new permit at the regular fee is needed.
What happens if I start construction before getting a permit?
Sec. 10-13(a)(3) imposes a penalty of $100 or double the normal permit fee, whichever is greater, capped at $2,000, in addition to the permit fee itself. Sec. 10-31 confirms double fees apply whenever work begins before the permit issues, and the Building Inspector can also issue a stop-work order.

Sources & Official References

Other rules in Janesville

All Janesville rules

Compare Janesville to another location·View the Wisconsin building safety overview

Get notified when Building Permits in Janesville, WI changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Permits in Nearby Cities

How other cities in Rock County handle building permits.

Beloit, WI
Some Restrictions
Milton, WI
Some Restrictions