Key Facts

Governing section
Sec. 7-127, Building Code
Application form
Written, Building Official form, Sec. 7-129
Exempt: sheds
One-story, up to 120 sq ft
Exempt: fences
Not over 6 feet high
Exempt: decks
No more than 30 inches above grade
Hazmat permit
Required if Fire Chief mandates it

Summary

Lee's Summit requires a permit before almost any construction, alteration, or system work on a building. Sec. 7-127 makes any owner or agent who wants to build, enlarge, alter, repair, move, demolish or change a building's occupancy, or touch its electrical, gas, mechanical, plumbing or elevator systems, apply to the Building Official first.

Any owner or authorized agent who intends to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, or to erect, install, enlarge, alter, repair, remove, convert or replace any electrical, gas, mechanical, plumbing, or elevator system, the installation of which is regulated by this Code, or to cause any such work to be done, shall first make application to the Building Official and obtain the required permit.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 55 | Unified Development Ordinance: Supplement 15).

Full Breakdown

Under Sec. 7-127 of the Lee's Summit Building Code, obtaining a permit is the default rule for any regulated construction or system work: new construction, additions, alterations, repairs, moving a structure, demolition, occupancy changes, and any electrical, gas, mechanical, plumbing or elevator installation. Projects involving hazardous materials may also need a separate hazardous materials permit before the building permit issues if the Fire Chief requires it. Sec. 7-129 requires the application to be filed in writing on a Building Official form before any permit issues.

Sec. 7-128 carves out a detailed list of exemptions so homeowners don't need a permit for minor work: retaining walls up to four feet tall, decks and walkways no more than thirty inches above grade with no roof, one-story sheds and playhouses up to 120 square feet, fences up to six feet, above-ground prefab pools under 5,000 gallons and less than twenty-four inches deep, painting and similar finish work, and swing sets. Electrical exemptions cover minor repairs like lamp replacement and connecting portable equipment to existing outlets; plumbing exemptions cover stopping leaks and replacing a water heater in a one- or two-family home.

None of these exemptions authorizes work that otherwise violates the Code, and emergency repairs still require a permit application submitted the next business day. Once a permit issues, Sec. 7-158 makes the work subject to inspection and requires it to stay accessible for the Building Official to review before it's covered up.

Violations & Fines

Building without a required permit is enforced as a Code violation, and Sec. 7-128's exemptions never authorize work that otherwise breaks the Code. Sec. 7-136 requires the permit to be displayed at the job site, and inspectors can assess reinspection fees under Sec. 7-160(K) when work isn't ready or corrections weren't made.

Frequently Asked Questions

Do I need a permit to build a shed in Lee's Summit?
Only if it's larger than what Sec. 7-128 exempts. A one-story detached shed, playhouse, or similar accessory structure doesn't need a permit as long as its floor area is 120 square feet or less; anything bigger needs a Sec. 7-127 permit.
What work always needs a building permit?
Sec. 7-127 requires a permit before you construct, enlarge, alter, repair, move, or demolish a building, change its occupancy, or install, alter or replace its electrical, gas, mechanical, plumbing or elevator systems, unless Sec. 7-128 specifically exempts the work.
Can I build a six-foot fence without a permit?
Yes. Sec. 7-128(A)(9) exempts fences that are not over six feet high from the permit requirement, though the fence still has to comply with any other applicable Code and zoning rules.

Sources & Official References

Other rules in Lee's Summit

All Lee's Summit rules

Compare Lee's Summit to another location·View the Missouri building safety overview

Get notified when Building Permits in Lee's Summit, MO changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.