Medford, MA Building Safety: Building Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit fee
$15 per $1,000 of construction cost
Application fee
$35
No permit before starting work
Quadruple fee charged
Fee schedule location
Appendix A, cross-ref. Sec. 10-35

Summary

A Medford building permit costs $15 per $1,000 of estimated construction cost for new construction, additions, alterations and repairs, plus a separate $35 application fee, under the Appendix A fee schedule tied to Sec. 10-35. Anyone who starts work before pulling that permit pays a quadrupled fee once the building commissioner's office catches the unpermitted work.

Sec. 10-35. - Building permit and inspection fees. The building permit and inspection fees are included in appendix A of these Revised Ordinances. ... (a) Schedule of Building Fees: 10-35

(1) Permit fees for new building; additions; alterations; and repairs: per $1,000.00 of estimated construction cost . . 15.00 Application fee . . 35.00 ... (10) Work started without a building permit . . Quadruple fee

Full Breakdown

Sec. 10-35 of the Revised Ordinances simply states that building permit and inspection fees are set out in Appendix A, so the substantive dollar amounts live in the city's consolidated fee schedule rather than in the chapter text itself. That schedule's Schedule of Building Fees, cross-referenced back to Sec. 10-35, prices permits for new building construction, additions, alterations, and repairs at $15.00 per $1,000.00 of estimated construction cost, with a separate $35.00 application fee due on top of that. The same schedule enforces the permit requirement financially rather than criminally: item (10), 'Work started without a building permit,' charges a quadruple fee once the building commissioner's office discovers the unpermitted work, meaning a project that skips the permit ends up paying roughly five times what a timely applicant pays for the same job.

Chapter 10, Article II adopts the Massachusetts State Building Code by reference under M.G.L.A. c. 143, § 98, so the substantive construction standards themselves come from the state code while Medford's own ordinance supplies the local fee and penalty structure that makes permitting worthwhile to do correctly the first time.

Violations & Fines

Building without a permit is punished financially: Appendix A's item (10) charges a quadruple fee once the building commissioner's office finds work that started without one. The underlying $15-per-$1,000 permit fee plus the $35 application fee still apply on top of that quadruple charge, so skipping the permit costs roughly five times the fee a timely applicant would have paid.

Frequently Asked Questions

How much does a building permit cost in Medford?
Under the Appendix A fee schedule referenced in Sec. 10-35, a permit for new construction, additions, alterations, or repairs costs $15 per $1,000 of estimated construction cost, plus a separate $35 application fee.
What if I start construction before getting a Medford building permit?
Appendix A's item (10) charges a quadruple fee for work started without a building permit, on top of the underlying $15-per-$1,000 fee, once the building commissioner's office catches the unpermitted work.
Where are Medford's building permit fees set out?
Sec. 10-35 of the Revised Ordinances states that building permit and inspection fees are included in Appendix A, the city's consolidated fee schedule covering every chapter of the code.

Sources & Official References

Other rules in Medford

All Medford rules

Compare Medford to another location·View the Massachusetts building safety overview

Get notified when Building Permits in Medford, MA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.