Medford, MA Building Safety: Electrical Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Notice deadline
Before starting or within 5 days after finishing
Fine for no notice
$20 (Sec. 10-66(a))
No application filed
Triple the normal fee (Sec. 10-67(b))
Additional inspection, defective work
$20 (Appendix A item 19)

Summary

Medford requires anyone installing electrical wiring or fixtures for hire to notify the superintendent of wires before starting, or within five days after finishing, under Sec. 10-66, tied to M.G.L.A. c. 143, § 3L. Skipping that notice draws a $20 fine, and doing electrical work with no application on file triples the normal permit fee under Sec. 10-67.

Sec. 10-66. - Fees. (a)Penalty for violation of article. No person shall install for hire any electrical wiring or fixtures subject to M.G.L.A. c. 143, § 3L, without first, or within five days after completing the work, giving notice to the superintendent of wires. Failure to comply with this section is punishable by a $20.00 fine. ... Sec. 10-67. - Permits not otherwise specified. (a)An additional charge in an amount set by the city and listed in appendix A of these Revised Ordinances will be made by this department and must be paid by the contractor, or other person doing the work, for each additional inspection resulting, in the opinion of this department, from defective work caused, in whole or in part, by the use of improper or unworkmanlike installation or incompletion of work.(b)The fee will be triple the amount of the normal fee for electrical installation for which no application was applied for, prior to the date work was performed. ... (19) Additional inspection for defective work . . 20.00 10-67

Full Breakdown

Sec. 10-66(a) puts a notice duty on anyone who installs electrical wiring or fixtures for hire under the state's electrical licensing statute, M.G.L.A. c. 143, § 3L: notify the superintendent of wires either before starting the job or within five days after finishing it. Failing that notice is punishable by a $20.00 fine under the same subsection. Sec. 10-67 layers on inspection-related charges that fall on the contractor or other person doing the work: an additional charge applies for each extra inspection the department has to make because of defective, improper, or unworkmanlike installation, and Sec.

10-67(b) triples the normal electrical fee outright when work goes forward with no application ever filed. Appendix A's electrical fee schedule prices that additional-inspection charge for defective work at $20.00 under item (19), cross-referenced back to Sec. 10-67, so a botched job can cost both the extra-inspection fee and, if there was never an application, the tripled base fee on top of it. Taken together, the notice deadline, the flat $20 fine for missing it, and the tripled fee for skipping the application entirely push every electrician toward filing paperwork before turning on a single circuit rather than explaining the work afterward.

Violations & Fines

Failing to notify the superintendent of wires before or within five days after wiring work is a $20.00 fine under Sec. 10-66(a). Doing electrical work with no permit application on file draws a tripled fee under Sec. 10-67(b), and defective work that needs a follow-up inspection costs $20.00 more under Appendix A item (19).

Frequently Asked Questions

Do I need to notify the city before doing electrical work in Medford?
Yes. Sec. 10-66(a) requires anyone installing wiring or fixtures for hire to notify the superintendent of wires before starting the job or within five days after finishing it, under authority of M.G.L.A. c. 143, § 3L.
What's the penalty for skipping the electrical work notice in Medford?
Sec. 10-66(a) sets a flat $20 fine for failing to give the required notice to the superintendent of wires, separate from any permit or inspection fees owed under Appendix A.
What if an electrician never files an application for the work?
Sec. 10-67(b) triples the normal electrical fee when work is done with no application ever filed, on top of any additional-inspection charges the defective work generates.

Sources & Official References

Other rules in Medford

All Medford rules

Compare Medford to another location·View the Massachusetts building safety overview

Get notified when Electrical Permits in Medford, MA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.