Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit expiration
12 months to start work or inspection
Suspension limit
180 days idle voids permit
Extensions
Up to 3 extensions of 180 days each
Civil penalty
$100-$1,000 per day of violation
Document retention
Plans kept 180 days after completion
Fee refund
Up to 80% if permit unused

Summary

In the City of Milpitas, the Building Official must review every permit application's construction documents, specifications and fee payment before issuing a permit under Milpitas Municipal Code Section II-1-8.01. A permit expires if work does not start, or an inspection is not made, within 12 months, or if work stops for 180 days, and every permit fee is set by City Council resolution.

The application, construction documents, specifications, computations and other data, filed by an applicant for permit shall be reviewed by the Building Official. Such documents may be reviewed by other departments of this jurisdiction to verify compliance with any applicable laws under their jurisdiction. If the Building Official finds that the work described in an application for a permit and the construction documents, specifications and other data filed therewith conform to the requirements of this Title and other pertinent laws and ordinances, and that the fees specified have been paid, the Building Official shall issue a permit therefore to the applicant. ... Every permit issued by the Building Official under the provisions of this Title shall expire by limitation and become null and void, if the building or work authorized by such permit is not commenced or an inspection made within 12 months from the date of such permit, or if the building or work authorized by such permit is suspended or abandoned at any time after the work is commenced for a period of 180 days. ... The fee for each permit shall be as set forth by resolution of the City Council.

Full Breakdown

Milpitas Municipal Code Title II, Chapter 1 governs permit issuance for every construction code the City has adopted, including the Building, Residential, Mechanical, Electrical, Plumbing, Property Maintenance, and Swimming Pool and Spa Codes (Section II-1-1.01). Before a permit issues, the Building Official reviews the application, construction documents, specifications and computations, and other City departments may review the same package for compliance with laws under their own jurisdiction (II-1-8.01). A permit can be issued for only part of a project, such as a foundation, before the rest of the plans are approved, but the holder proceeds at their own risk with no guarantee the remainder will be granted.

No Building or Occupancy Permit may issue until any conditions the Planning Commission or City Council attached to a development or subdivision have been satisfied (II-1-3.07). Once issued, a set of approved plans must stay on the jobsite and the Building Official keeps a second set for at least 180 days after the work is finished (II-1-8.02). A permit expires and becomes void if work is not commenced or inspected within 12 months, or if it is suspended or abandoned for 180 days; recommencing then costs half the original fee unless the gap exceeds 360 days, in which case a full new fee applies, and the Building Official may grant up to three 180-day extensions on written request (II-1-8.04).

The Building Official can also suspend or revoke a permit issued in error or on false information (II-1-8.05). Every permit fee and plan review fee is set by City Council resolution (II-1-9.01, II-1-9.02), with refunds of up to 80 percent available for cancelled plan review or unused permits (II-1-9.03). Building without a required permit is unlawful under Section II-1-5.01 and can draw a civil penalty of $100 to $1,000 per day under Section II-1-5.04.

Violations & Fines

Constructing, altering, repairing or demolishing a building without the required permit is unlawful under Milpitas Municipal Code Section II-1-5.01. The Building Official can pursue a civil penalty of not less than $100 and up to $1,000 per day for each day the violation continues under Section II-1-5.04, on top of inspection and abatement costs, and the City may petition Santa Clara County Superior Court to collect it. The Building Official may also suspend or revoke a permit obtained through incorrect information under Section II-1-8.05.

Frequently Asked Questions

How long is a Milpitas building permit valid?
Twelve months from issuance to start work or get an inspection, under Milpitas Municipal Code Section II-1-8.04. If work begins but then stops for 180 days, the permit is void; you can restart for half the original fee if the gap is under 360 days, or a full new fee after that.
What happens if I build without a permit in Milpitas?
It's unlawful under Section II-1-5.01 of the Municipal Code, and the Building Official can seek a civil penalty of $100 to $1,000 per day the violation continues under Section II-1-5.04, collected through Santa Clara County Superior Court, on top of any inspection or abatement costs the City incurs.
Can I extend my building permit before it expires?
Yes. Milpitas Municipal Code Section II-1-8.04 lets the Building Official grant a written extension of up to 180 days at a time if you show the delay is beyond your control, capped at three extensions total, so you cannot keep an unfinished permit open indefinitely.
Who sets Milpitas building permit fees?
The City Council, by resolution, under Milpitas Municipal Code Sections II-1-9.01 and II-1-9.02, which cover both the permit fee itself and any plan review fee. Up to 80 percent of a plan review or permit fee can be refunded if you cancel before review starts or never use the permit.

Sources & Official References

Other rules in Milpitas

All Milpitas rules

California rules heatmap·Compare Milpitas to another location·View the California building safety overview

Get notified when Building Permits in Milpitas, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Permits in Nearby Cities

How other cities in Santa Clara County handle building permits.

Sunnyvale, CA
Some Restrictions
Santa Clara, CA
Some Restrictions
San Jose, CA
Some Restrictions
Mountain View, CA
Some Restrictions