Key Facts

Adopted code
2025 California Plumbing Code (Title 24, Pt. 5)
Appendices adopted
A, B, C, D, I and M, § II-7-1.01
Permit issuance
Building Official approves plans/fees, § II-1-8.01
Permit expiration
12 months to start/inspect, § II-1-8.04
Civil penalty
$100-$1,000 per day, § II-1-5.04
Enforcing office
Building Official, Planning and Neighborhood Services

Summary

The City of Milpitas requires a plumbing permit for work covered by the 2025 California Plumbing Code, adopted at Municipal Code § II-7-1.01. The Building Official reviews plans and fees before issuing the permit, and unpermitted plumbing or drainage work is declared a public nuisance carrying a civil penalty of up to $1,000 per day.

The 2025 California Plumbing Code, published and copyrighted by the International Association of Plumbing and Mechanical Officials and the California Building Standards Commission in Part 5 of Title 24 of the California Code of Regulations, is hereby adopted and referred to, and by this reference expressly incorporated and made a part of this Chapter as though fully set forth herein. The adoption includes Appendices A, B, C, D, I, and M. The 2025 California Plumbing Code shall be designated and referred to as the "Plumbing Code" for the City of Milpitas. There is one copy of said code on file in the office of the Building Official for use and examination by the public.

Full Breakdown

Milpitas adopted the 2025 California Plumbing Code, published by the International Association of Plumbing and Mechanical Officials and the California Building Standards Commission in Part 5 of Title 24 of the California Code of Regulations, as the city's Plumbing Code under Municipal Code § II-7-1.01 (Ord. No. 65.155, § 3, adopted 9/2/25), including Appendices A, B, C, D, I and M. Chapter 7 carries no local amendment section, so administration runs through Title II Chapter 1: the Building Official reviews the application, construction documents and fees, then issues the plumbing permit once everything conforms to the code and other applicable ordinances (§ II-1-8.01).

Approved documents are kept on file for at least 180 days, and a set must stay on the jobsite while work is underway (§ II-1-8.02). A plumbing permit expires if the work is not commenced or inspected within 12 months, or if it is suspended or abandoned for more than 180 days; resuming then costs half the original permit fee unless the lapse runs past 360 days, in which case a full new fee applies (§ II-1-8.04). Installing, altering or repairing plumbing or drainage lines, equipment or systems contrary to Title II is unlawful (§ II-1-5.01) and is expressly declared a public nuisance by § II-1-6.01, which names plumbing and drainage work alongside electrical and mechanical work.

The City can seek a civil penalty of not less than $100 nor more than $1,000 per day of violation under § II-1-5.04, and permit decisions may be appealed to the Building Official under § II-1-4.01.

Violations & Fines

Installing, altering or repairing plumbing or drainage lines, equipment or systems in violation of Title II is unlawful under § II-1-5.01 and is specifically named as a public nuisance in § II-1-6.01. The City may pursue a civil penalty of $100 to $1,000 per day of violation under § II-1-5.04, in addition to inspection and abatement costs, and can petition Santa Clara County Superior Court to recover it.

Frequently Asked Questions

What plumbing code applies in the City of Milpitas?
Milpitas has adopted the 2025 California Plumbing Code, published by the International Association of Plumbing and Mechanical Officials and the California Building Standards Commission in Title 24, Part 5, as its Plumbing Code under Municipal Code § II-7-1.01, including Appendices A, B, C, D, I and M.
Do I need a permit for plumbing work in Milpitas?
Yes. Under Municipal Code § II-1-8.01, the Building Official reviews the application, construction documents, specifications and required fees, and issues the plumbing permit once the proposed work conforms to the adopted Plumbing Code and every other applicable law or ordinance.
How long is a Milpitas plumbing permit good for?
It expires under § II-1-8.04 if the work is not commenced or inspected within 12 months of issuance, or if the work is suspended or abandoned for more than 180 days; restarting then costs half the original fee unless the lapse exceeds 360 days.
What happens if plumbing work is done without a permit?
It is unlawful under § II-1-5.01, and § II-1-6.01 specifically declares unpermitted installation, alteration or repair of plumbing or drainage lines a public nuisance. The City can seek a civil penalty of $100 to $1,000 per day of violation under § II-1-5.04.
How long must approved plumbing plans stay on the jobsite?
Section II-1-8.02 requires one set of the approved construction documents to be kept on the site of the work at all times while the permitted plumbing work is in progress, with a separate set retained by the Building Official for at least 180 days.

Sources & Official References

Other rules in Milpitas

All Milpitas rules

California rules heatmap·Compare Milpitas to another location·View the California building safety overview

Get notified when Plumbing Permits in Milpitas, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Plumbing Permits in Nearby Cities

How other cities in Santa Clara County handle plumbing permits.

Sunnyvale, CA
Some Restrictions
Santa Clara, CA
Some Restrictions
Mountain View, CA
Some Restrictions
San Jose, CA
Some Restrictions