Sammamish, WA Building Safety: Building Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified August 2026

Key Facts

General rule
Permit required before construction/alteration/demolition
Applies to
Buildings, structures, gas, mechanical, plumbing systems
Permit validity
2 years from issuance
Extension
One 1-year extension, half fee, filed within 30 days
Application expiration
18 months if no permit issued
Unpermitted work
Stop work order plus special investigation fee

Summary

Sammamish requires a City permit before almost any construction, alteration, demolition or occupancy change. SMC 16.20.195 obligates the owner or an authorized agent to apply to the permit center and obtain the required permit before starting work on a building, structure, or a regulated gas, mechanical or plumbing system.

Any owner or owner's authorized agent who intends to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, or to erect, install, enlarge, alter, repair, remove, convert or replace any gas, mechanical or plumbing system, the installation of which is regulated by Chapter 16.05 SMC, or to cause any such work to be done, shall first make application to the permit center and obtain the required permit.

View official code

Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through Ordinance O2026-598, and legislation passed through August 18, 2026).

Full Breakdown

195 sets the baseline: any owner or owner's authorized agent who intends to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, or to erect, install, enlarge, alter, repair, remove, convert or replace a regulated gas, mechanical or plumbing system, must first apply to the permit center and obtain the permit before the work, or causing the work to be done, begins. 215. 220, and no building permit issues until every related project approval, including SEPA review, subdivision, PUD, conditional use, variance, shoreline and critical areas approvals, is complete and its fees and conditions satisfied. 222. 237, and an extended permit still expires no later than three years after original issuance. 225.

Violations & Fines

Starting work before a permit issues triggers SMC 16.20.355: the City can order a stop to the work and charge a special investigation fee on top of the permit fee, and where structural conformance can't be visually confirmed, the owner must hire a licensed design professional to certify the work's integrity. SMC 16.20.240 lets the building official suspend or revoke a permit issued in error or violated in the field, and continued work after a stop work order draws civil penalties under Chapter 23.100 SMC.

Frequently Asked Questions

When do I need a building permit in Sammamish?
SMC 16.20.195 requires a permit before you construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, or work on a regulated gas, mechanical or plumbing system. You apply through the City's permit center before the work, or hiring someone to do the work, begins.
How long is a Sammamish building permit good for?
Two years from the date of issuance, under SMC 16.20.235. The building official can approve one written extension of up to one additional year if you request it within 30 days of the original expiration, submit a construction schedule, and pay half the original permit fee, per SMC 16.20.237.
What happens if I start construction before getting a permit?
SMC 16.20.355 authorizes a stop work order and a special investigation fee on top of the required permit fees. If the City can't visually confirm structural conformance, you may have to hire a licensed design professional to certify the work, and continuing after a stop work order draws civil penalties under Chapter 23.100 SMC.

Sources & Official References

Other rules in Sammamish

All Sammamish rules

Compare Sammamish to another location·View the Washington building safety overview

Get notified when Building Permits in Sammamish, WA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Permits in Nearby Cities

How other cities in King County handle building permits.

Renton, WA
Some Restrictions
Seattle, WA
Some Restrictions
Kent, WA
Some Restrictions
Auburn, WA
Some Restrictions
Bellevue, WA
Some Restrictions
Federal Way, WA
Some Restrictions