Troup County, GA Building Safety: Building Permits (2026)
Key Facts
- Enforcing official
- Community Development Director
- Permit lapses if
- work not begun within 6 months
- Extension available
- up to 90 days, written request
- Fees set by
- Board of Commissioners fee schedule
- Appeals go to
- Construction Board of Adjustment and Appeals
Summary
In unincorporated Troup County, anyone who wants to construct, enlarge, alter, repair, move, demolish or change the occupancy of a building, or install regulated electrical, gas, mechanical or plumbing systems, must apply to the Community Development Director and obtain a permit before starting work.
Before issuing a building permit or mobile home permit, the Community Development Director shall forward copies of the application to the health department, the Community Development Director, and other departments for which approval is necessary. Upon favorable approval of all concerned, the Community Development Director may issue a permit. Permits shall become invalid if construction is not begun within six (6) months of the date of issuance. ... Fees for building permits are to be governed by the fee schedule approved by the Board of Commissioners and maintained by the Community Development Department. ... When required. Any owner, authorized agent, or contractor who desires to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, or to erect, install, enlarge, alter, repair, remove, convert or replace any electrical, gas, mechanical, or plumbing system, the installation of which is regulated by the construction codes, or to cause any such work to be done, shall first make application to the Community Development Director and obtain the required permit for the work.
Full Breakdown
Section 2.3(1) requires an owner, agent or contractor to make application to the Community Development Director and obtain a permit before constructing, enlarging, altering, repairing, moving, demolishing or changing the occupancy of a building, or before touching a regulated electrical, gas, mechanical or plumbing system. Applications must include a site plan showing property lines, easements, structures, soil conditions, terrain and parking, plus a construction drawing when the Director requires one (Sec. 2.1(1)(a)-(b)). The Director forwards copies to the health department and other reviewing departments, and can issue the permit only after all concerned approve; the permit then becomes invalid if construction has not begun within six months (Sec.
2.1(1)(c)). Fees follow the schedule the Board of Commissioners maintains through the Community Development Department (Sec. 2.1(2)), and a permit is denied outright if the property has an open zoning, subdivision, or other legal violation until it is cleared (Sec. 2.1(4)). Section 2.3(2) exempts specific minor mechanical work, such as portable heating, ventilation or cooling equipment and self-contained refrigeration units with 10 pounds or less of refrigerant on a motor of one horsepower or less. An application for any permit is deemed abandoned six months after filing if no permit issues, though the Director may grant 90-day extensions for justified delays (Sec.
2.3(6)). Contractors must supply their state license number, where the state requires one, before the county will issue their permit (Sec. 2.7). Disputed decisions go to the Construction Board of Adjustment and Appeals, which must meet within 30 days of a written notice of appeal (Sec. 2.14).
Violations & Fines
Starting work before a permit issues draws a penalty the Board of Commissioners sets under Sec. 2.9(2), on top of the required fee, and does not excuse compliance. Because the general Code penalty applies whenever a specific fine is not set, unpermitted building work can also be prosecuted under Troup County Code § 1-19 for a fine up to $1,000, up to six months in jail, or both, with each day of continued violation a separate offense.
Frequently Asked Questions
Do I need a permit to add onto my house in unincorporated Troup County?
How long is a Troup County building permit valid?
What could get my building permit application denied?
Is any work exempt from the permit requirement?
Sources & Official References
Other rules in Troup County
Compare Troup County to another location·View the Georgia building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.