Skip to main content
CityRuleLookup

Westfield, IN Building Safety: Building Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Building code source
Adopted by reference, § 14-31
Single-family permit fee
$600 + $.11/sq. ft.
Non-residential new construction fee
$600 + $.22/sq. ft.
Building without a permit (residential)
$500 penalty
Building without a permit (non-residential)
$1,500 penalty
Occupying without certificate of occupancy
$2,500 (res.) / $5,000 (non-res.)

Summary

The City of Westfield, Indiana adopts the Building Code of the City of Westfield by reference and charges building permit fees for nearly every category of construction, from single-family homes to commercial additions. Starting construction without the required permit, or occupying a structure without a certificate of occupancy, carries its own steep penalty.

(2)Building fees: ... Residential Single-family/two-family/tri-quad dwelling $600 +$.11/sq. ft. Multi-family dwelling $750 +$.11/sq. ft. ... Non-Residential New Construction $600 +$.22/sq. ft. Remodel/Tenant Finish $350 +$.22/sq. ft. Commercial Addition $600 +$.22/sq. ft. ... Occupying Structure without Certificate of Occupancy

- Residential $2,500

- Non-Residential $5,000 Commencing Construction without Required Permit(s):

- Residential $500

- Non-Residential $1,500

Full Breakdown

Sec. 14-31 incorporates "Section 15.04.010 of the city Code of 1990... the Building Code of the City of Westfield, Indiana" by reference as the governing building code, administered by the community development department. Sec. 14-131(2) then sets the actual permit fees that apply once that code requires a permit: $600 plus $.11 per square foot for a single-family, two-family or tri-quad dwelling, $750 plus $.11 per square foot for a multi-family dwelling, $250 plus $.11 per square foot for a residential accessory structure such as a pool or foundation, and $150 plus $.11 per square foot for a residential addition.

Non-residential work is billed at $600 plus $.22 per square foot for new construction, $350 plus $.22 per square foot for a remodel or tenant finish, and $600 plus $.22 per square foot for a commercial addition. Separate line items cover a $110 certificate of occupancy, a $150 demolition or building-relocation permit, and a $350-per-month temporary building or sales trailer permit. The code also prices the consequence of skipping the process: commencing construction without the required permit costs $500 for a residential project and $1,500 for a non-residential one, and occupying a structure before its certificate of occupancy is issued costs $2,500 residential or $5,000 non-residential.

Agricultural buildings with major electrical, plumbing, sewage or water installations are billed at the same $110 plus $.11-per-square-foot rate as those without, so the fee schedule does not exempt farm buildings from the permit requirement.

Violations & Fines

Building without first obtaining the required permit is a distinct, priced violation under Sec. 14-131: $500.00 for a residential project and $1,500.00 for a non-residential one. Occupying a completed structure before the city issues a certificate of occupancy adds a separate $2,500.00 (residential) or $5,000.00 (non-residential) charge on top of the standard permit fee, and these amounts are collected by the economic and community development department.

Frequently Asked Questions

Does Westfield require a building permit for a new house?
Yes. Sec. 14-131(2) prices a single-family, two-family or tri-quad dwelling permit at $600 plus $.11 per square foot, collected by the economic and community development department under the Building Code of the City of Westfield adopted in Sec. 14-31.
What happens if I start construction without a permit in Westfield?
Sec. 14-131 imposes a separate charge for commencing construction without the required permit: $500.00 for a residential project and $1,500.00 for a non-residential one, on top of whatever permit fee is eventually due.
Can I move into a new house before it's finished with the city?
No. Occupying a structure before the city issues its certificate of occupancy costs an additional $2,500.00 for residential projects and $5,000.00 for non-residential projects under Sec. 14-131, separate from the standard certificate of occupancy fee.
Is there a permit fee for a home addition in Westfield?
Yes, Sec. 14-131 sets a residential addition fee at $150 plus $.11 per square foot, while a commercial addition is billed at $600 plus $.22 per square foot.

Sources & Official References

Other rules in Westfield

All Westfield rules

Compare Westfield to another location·View the Indiana building safety overview

Get notified when Building Permits in Westfield, IN changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.