Key Facts

Permit required for
Electrical systems and equipment work
Governing section
Fayette County Code Sec. 102-1138
Adopted code
National Electrical Code (§ 102-22)
Emergency filing window
Next business day
Low-voltage exemption
Under 25 volts, 50 watts max
Permit expiration
180 days if work not started

Summary

Electrical work in unincorporated Fayette County requires a permit from the code official under Fayette County Code Sec. 102-1138, which also requires the permit to be kept on the premises and available for inspection. The county enforces the National Electrical Code, adopted under Sec. 102-22, with a short list of minor exemptions at Sec. 102-1140.

These county ordinances apply to unincorporated areas of Fayette County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

Permits required by the electrical code shall be obtained from the code official. Permit fees, if any, shall be paid prior to issuance of the permit. Issued permits shall be kept on the premises designated therein at all times and shall be readily available for inspection by the code official. If a licensed contractor performs work without obtaining any necessary permit, there is a rebuttable presumption that the contractor willfully and deliberately violated the building laws of this jurisdiction.

Full Breakdown

Fayette County Code Sec. ' Sec. 102-1078 confirms the electrical code enforced is the National Electrical Code as adopted in Sec. 102-22. Sec. 102-1139(a) requires an owner, authorized agent or contractor who wants to construct, enlarge, alter, repair, move, demolish or change the occupancy of a building, or to erect, install, alter, repair, remove, convert or replace electrical systems or equipment regulated by the electrical code, to apply to the code official first. A small set of exemptions appears at Sec. 102-1140: listed cord-and-plug temporary decorative lighting, reinstalling attachment-plug receptacles (not the outlets), repair or replacement of branch-circuit overcurrent devices of the same capacity in the same location, temporary experimental wiring in suitable laboratories, and wiring or equipment operating below 25 volts and incapable of supplying more than 50 watts.

Emergency repairs get a grace period under Sec. 102-1139(b): the permit application must reach the department of electrical inspection by the next business day. Permits expire if work is not commenced within 180 days of issuance or is suspended for 180 days under Sec. 102-1191, and the code official may grant one 180-day extension under Sec. 102-1192.

Violations & Fines

Sec. 102-1138 states that 'if a licensed contractor performs work without obtaining any necessary permit, there is a rebuttable presumption that the contractor willfully and deliberately violated the building laws of this jurisdiction.' Sec. 102-1196 authorizes the code official to suspend or revoke a permit issued in error, based on incorrect or incomplete information, or issued in violation of any ordinance or provision of the electrical code. Sec. 102-1140 also warns that an exemption from the permit requirement 'shall not be deemed to grant authorization for any work to be done in violation of the provisions of the electrical code or any other laws or ordinances of this jurisdiction.'

Frequently Asked Questions

Do I need a permit for electrical work in unincorporated Fayette County?
Yes. Sec. 102-1138 requires a permit from the code official for electrical systems and equipment work regulated by the National Electrical Code, and the permit must stay on the premises and be available for inspection until the job is done.
Is any electrical work exempt from a permit?
Sec. 102-1140 exempts a short list of minor items: listed temporary decorative lighting, reinstalling attachment-plug receptacles, replacing branch-circuit overcurrent devices of the same rating in the same spot, lab experimental wiring, and wiring or equipment under 25 volts and 50 watts.
What happens if a licensed contractor does electrical work without a permit?
Sec. 102-1138 creates a rebuttable presumption that the contractor willfully and deliberately violated the county's building laws, and Sec. 102-1196 lets the code official suspend or revoke any permit issued on incorrect information or in violation of the electrical code.

Sources & Official References

Other rules in Fayette County

All Fayette County rules

Compare Fayette County to another location·View the Georgia building safety overview

Get notified when Electrical Permits in Fayette County, GA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.