Fayette County, GA Building Safety: Building Inspections (2026)
Key Facts
- Inspecting officer
- the building official
- Site access
- work must stay exposed until approved
- Stages
- footing, slab, frame, lath, energy, final
- New homes
- lot and foundation survey also required
- Covered without inspection
- triggers special investigation
- Governing law
- Fayette County Code §§ 102-284, 102-286
Summary
Fayette County Code § 102-284 keeps every permitted job open to inspection by the building official until approved, and Code § 102-286 lists the required stages, from footing and foundation through framing to the final inspection once all permitted work is done.
Construction or work for which a permit is required shall be subject to inspection by the building official and such construction or work shall remain accessible and exposed for inspection purposes until approved. ... (1)Footing and foundation inspection. Footing and foundation inspection shall be made after excavations for footings are complete and any required reinforcing steel is in place. ... (4)Frame inspection. Framing inspections shall be made after the roof deck or sheathing, all framing, fireblocking and bracing are in place and pipes, chimneys and vents to be concealed are complete and the rough electrical, plumbing, heating wires, pipes and ducts are approved. ... (11)Final inspection. The final inspection shall be made after all work required by the building permit is completed.
Full Breakdown
Under Code § 102-284, construction or work covered by a building permit stays subject to inspection by the building official, and the permit holder has to keep the work accessible and exposed for inspection until it is approved; an inspection approval never excuses a violation of the building code or any other county ordinance. It is the permit applicant's job, not the county's, to keep the site open for inspection, and neither the building official nor the county is liable for the cost of removing or replacing material to allow an inspection to happen.
Code § 102-286 lays out the required inspection stages in sequence: a footing and foundation inspection once excavation is complete and reinforcing steel is in place; a concrete slab and under-floor inspection before concrete is poured or the subfloor goes down; a frame inspection once the roof deck, framing, fireblocking, bracing, and rough electrical, plumbing and heating work are all in and approved; a lath and gypsum board inspection; energy efficiency inspections covering insulation, fenestration, duct and HVAC values; a lot and foundation survey for new single-family homes and for accessory structures, pools and additions built within two feet of a setback line; and a final inspection once all permitted work is complete. Section 102-289 bars work from moving past the point of each inspection without the building official's approval, and section 102-288 puts the burden on the permit holder to notify the building official when work is ready to be checked.
Violations & Fines
Work covered without first getting the required inspection approval forces a special investigation before the county will approve any later inspection, and covered work has to be exposed again to allow the missed inspection to happen (Code § 102-290). Building past the point signed off in a prior inspection without the building official's approval is likewise a violation (Code § 102-289).
Frequently Asked Questions
What inspections does Fayette County require during construction?
Who is responsible for scheduling a Fayette County building inspection?
What happens if work is covered up before it's inspected?
Sources & Official References
Other rules in Fayette County
Compare Fayette County to another location·View the Georgia building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.