Key Facts

Governing section
Gretna Code of Ordinances § 10-113
Threshold
Applies above 32 volts open-circuit potential
Application fee
$15.00 nonrefundable, plus per-amp/circuit fees
Engineer stamp required
Over 200-amp single-phase or 150-amp three-phase
Cash deposit
Minimum $25.00 kept on file, § 10-117
Violation fee
$300.00 for unpermitted electrical work, § 10-41(c)

Summary

In the City of Gretna, anyone installing, repairing, or altering wiring carrying more than 32 volts open-circuit potential has to file an application for a permit with the electrical inspector before starting work, under Code of Ordinances § 10-113. No electrical work begins until that permit issues, plans over 200-amp single-phase or 150-amp three-phase service need a state-registered electrical engineer's stamp, and substandard work can cost the contractor both the permit and the license.

(a)Every person proposing to install, repair or alter any electrical equipment of wires, designated to carry electricity at a different potential of open circuit voltage over 32 volts, for any purpose or service in, or on, any building or premises, shall file an application for a permit with the electrical inspector. No work may commence until a permit has been issued. ... All work shall be done in a workmanlike manner and shall conform to all the requirements of this Code. Faulty or substandard work shall be cause for revoking a permit, and suspending or revoking a license.

Full Breakdown

Chapter 10, Article III, Division 2 of the Gretna Code puts electrical permitting in the hands of the electrical inspector. Under § 10-113(a), every person installing, repairing, or altering electrical equipment carrying more than 32 volts open-circuit potential in or on a Gretna building or premises has to file a permit application first, and no work starts until the electrical inspector issues that permit. The application, per § 10-113(b), spells out the installation or repair down to square footage, outlet count, circuit sizes, motor horsepower and voltage, and the purpose the building will serve once the work is done; faulty or substandard work is grounds for revoking the permit and suspending or revoking the contractor's license.

Under § 10-114, drawings and specifications go with the application, and a state-registered electrical engineer has to stamp the plans for any service over 200-amp single-phase or 150-amp three-phase. The electrical inspector, under § 10-65, can enter any building or premises during reasonable hours to inspect, test, or reinspect wiring, and interfering with that inspection is unlawful. 00 for elevator or escalator wiring, listed in § 10-116. 00. Concealing wiring before inspection is barred under § 10-149(d), which ties compliance back to the National Electrical Code, and the electrical inspector will not sign a certificate of approval until the work has been inspected and found to meet every requirement of the article.

Violations & Fines

Working without a filed permit triggers an investigation under § 10-41(c), and the building official can impose a $300.00 violation fee on top of the required permit fees. Faulty or substandard work is grounds for revoking the permit itself and for suspending or revoking the electrician's license under § 10-113(b). Concealed, uninspected wiring must be exposed again at the installer's own expense. The Code's general penalty at § 1-8 also applies: a fine up to $500.00, with each continuing day a separate offense.

Frequently Asked Questions

Do I need a permit for minor electrical work in Gretna?
Yes, if the wiring carries more than 32 volts of open-circuit potential. Section 10-113(a) requires anyone installing, repairing, or altering such equipment in or on a Gretna building to file an application with the electrical inspector first, and no work can start until that permit is issued.
What happens if my electrician does substandard work?
Under § 10-113(b), faulty or substandard work is itself grounds for the electrical inspector to revoke the permit and to suspend or revoke the electrician's license. The contractor stays responsible for defects discovered even after a certificate of approval issues, under § 10-149(a).
Does a big residential service upgrade need an engineer's stamp in Gretna?
Yes, above certain sizes. Section 10-114(a) requires drawings and specifications stamped by a state-registered electrical engineer for any installation over a 200-ampere single-phase service or a 150-ampere three-phase service; smaller jobs only need drawings if the electrical inspector asks for them.

Sources & Official References

Other rules in Gretna

All Gretna rules

Compare Gretna to another location·View the Louisiana building safety overview

Get notified when Electrical Permits in Gretna, LA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.