Gretna, LA Building Safety: Building Inspections (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing section
Gretna Code of Ordinances § 10-45
Enforcing official
City building official
Placard requirement
Posted until certificate of completion issues
Slab certificate deadline
Within 21 days of the concrete pour
Non-permitted work fee
$300.00 investigation fee, § 10-40
General penalty
Fine up to $500.00 per day, § 1-8

Summary

In the City of Gretna, the building official inspects every stage of construction under Code of Ordinances § 10-45, from a pre-permit review through the final inspection required before a certificate of completion issues. No permitted work starts until the building permit placard is posted on site, and new construction gets no foundation inspection until a certified elevation and setback certificate is filed with the building department.

(a)Existing building inspections. Before issuing a building permit, the building official may examine or cause to be examined any building, or service system for which an application or filing has been submitted to install, enlarge, alter, repair, move, demolish, or change the occupancy. The building official may periodically inspect all buildings, structures, and service systems, which are required to be maintained in compliance with this article. ... (g)For all new buildings, the following prerequisites shall be met: A certified form elevation certificate and a certified site plan of the forms showing all building setbacks must be presented to the building section of the department prior to the slab inspection being scheduled or performed. No foundation inspection shall be performed until a certificate is issued by the building official stating the elevation and setbacks for the construction are in accordance with the code and are approved. Within 21 days of the placement of the concrete, a certified slab elevation certificate must be presented to the building department.

Full Breakdown

Section 10-45 lays out the city's building-inspection framework in Chapter 10, Article II, Division 2. Before a building permit issues, the building official can examine any building or service system named in an application to install, enlarge, alter, repair, move, demolish, or change occupancy, and can periodically re-inspect buildings and service systems required to stay in compliance. When materials or assemblies are manufactured outside the city, the building official can inspect them at the point of fabrication, with the cost borne by the party wanting to use the materials here; the building official can also accept certification from an approved third-party testing agency instead.

Every job that receives a permit or filing gets periodic inspection, and every building, structure, or service system gets a final inspection once work is complete, before a certificate of completion issues. No one starts permitted work until the permit is issued and the building permit placard, protected from weather and kept in good condition, is conspicuously posted where the building official can observe it; that posting authorizes the building official onto the premises to perform required duties, and it stays up until the certificate of completion is issued.

Residential home improvement contractors can post a job-site sign between two feet by two feet and two feet by three feet. For every new building, a certified form elevation certificate and a certified site plan showing all building setbacks go to the building section before the slab inspection is scheduled; no foundation inspection happens until the building official certifies the elevation and setbacks match the code, and a certified slab elevation certificate is due within 21 days of the concrete pour. S. 24 with the Louisiana Uniform Construction Code Council and the city, per § 10-39(d), can perform some construction inspections the city accepts, though the city is never required to accept them in place of its own building department inspections.

Violations & Fines

Starting work without an issued permit or without the placard posted triggers a building investigation under § 10-40, and the building official can impose a $300.00 violation fee on top of the required permit or plan-processing fees. Failing a required inspection stops the job until the building official signs off on the cited deficiencies. The Code's general penalty at § 1-8 also applies: a fine up to $500.00, with each day a violation continues charged as a separate offense.

Frequently Asked Questions

Does Gretna inspect a foundation before I pour concrete?
Yes. Under § 10-45(g), a certified form elevation certificate and a certified site plan showing all building setbacks must reach the building section before the slab inspection can be scheduled, and no foundation inspection happens until the building official certifies the elevation and setbacks. A certified slab elevation certificate is then due within 21 days of the concrete pour.
What happens if I build without a permit in Gretna?
The building official opens an investigation under § 10-40 and can impose a $300.00 violation fee, charged in addition to the permit or plan-processing fees still owed. The general penalty in § 1-8 also applies, allowing a fine up to $500.00, with each continuing day treated as a separate offense.
Can I use a private inspector instead of the city's building official?
Only for narrow purposes. Third-party providers registered with the Louisiana Uniform Construction Code Council and the city under § 10-39(d) can perform some construction inspections, but the city is never required to accept a third-party inspection instead of its own building department inspection.

Sources & Official References

Other rules in Gretna

All Gretna rules

Compare Gretna to another location·View the Louisiana building safety overview

Get notified when Building Inspections in Gretna, LA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.