Key Facts

Adopted code
1978 National Electrical Code
Permit threshold
Contract/cost over $100
Permitting official
County Building Commissioner
Minimum permit fee
$5 (costs up to $5,000)
Inspection fee
$7.50 per inspection
Max penalty
$2,500 per day (§ 10.99)

Summary

Howard County adopted the 1978 National Electrical Code by reference under § 150.03(A)(3), and § 150.05 makes it unlawful to start any electrical work with a contract price or estimated cost over $100 without first getting the Building Commissioner's approval and a permit.

These county ordinances apply to unincorporated areas of Howard County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

(3) The National Electrical Code, 1978 edition, adopted by the National Fire Protection Association. ... (A) Prior to the construction of any building, structure, dwelling or any part thereof, no extension, repair or alteration of any existing building, no plumbing, no electrical work, no heating work, no ventilation work, nor air conditioning work having a contract price or estimated cost of more than $100 shall be started until a statement in writing of the work proposed to be done shall first be submitted by the contractor or individual in charge of the work to and approved by the Building Commissioner, and a permit issued by him or her for the proposed construction, alteration, repair or extension work.

Full Breakdown

03(A)(3) adopts the National Electrical Code, 1978 edition, by reference as the wiring standard governing construction in the county, alongside the Indiana Construction Rules and Regulations, the One- and Two-Family Dwelling Code, the Plumbing Rules and Regulations and the Mechanical Rules and Regulations; copies of all five are on file with the County Building Commission at the Courthouse. 05(A) requires that before any electrical work with a contract price or estimated cost over $100 begins, the contractor or person in charge must submit a written statement of the proposed work and get it approved by the Building Commissioner, who issues the permit.

The Commissioner can require detailed plans and specifications, keeps a copy on file, and must approve any change from those plans before the change is made; the Commissioner must refuse a permit if the proposed work would violate any state statute or county ordinance. 50 fee for each required inspection. No permit is needed for painting or other cosmetic work that does not alter or extend the building. C. 5, to the Executive Committee of the Administrative Building Council of Indiana, a statute the code's own editor's note flags as since repealed.

Violations & Fines

Starting electrical work costing more than $100 without an approved Building Commissioner's permit violates § 150.02 and § 150.05, punishable under the county's general penalty section, § 10.99, by a fine of up to $2,500, with each day the violation continues counted as a separate offense. The Commissioner may also issue a stop-work order under § 150.08 halting the job until the violation is corrected.

Frequently Asked Questions

Does Howard County require a permit for electrical work?
Yes. Section 150.05(A) requires a Building Commissioner permit before starting any electrical work with a contract price or estimated cost over $100, and the county has adopted the 1978 National Electrical Code by reference under § 150.03(A)(3) as the governing wiring standard.
How much does an electrical permit cost in Howard County?
Permit and inspection fees follow the sliding scale in § 150.06, starting at $5 for work costing up to $5,000 and rising to $57.50 plus $0.35 per $1,000 above $100,000, capped at $100, plus a separate $7.50 fee for each required inspection.
What happens if I do electrical work without a permit in unincorporated Howard County?
The Building Commissioner can issue a stop-work order under § 150.08 halting the job, and the violation is fined under the county's general penalty section, § 10.99, up to $2,500, with each day of continued violation treated as a separate offense.

Sources & Official References

Other rules in Howard County

All Howard County rules

Compare Howard County to another location·View the Indiana building safety overview

Get notified when Electrical Permits in Howard County, IN changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.