Huntington Park, CA Building Safety: Electrical Permits (2026)
Key Facts
- Permit issued by
- The building official
- Adopted code
- 2019 Los Angeles County Electrical Code (Title 27)
- Separate plan review trigger
- Equipment rated at 400 amperes or larger
- Temporary decorative lighting exemption
- Not installed for more than 90 days
- Penalty
- Misdemeanor or infraction, City Attorney's choice
- Current chapter effective
- Ord. 2020-981, February 21, 2020
Summary
In the City of Huntington Park, California, no one can erect, alter, install, repair, move, improve, remove, connect or convert electrical equipment without first obtaining an electrical permit from the building official. The City Council adopted the 2019 Los Angeles County Electrical Code, which adopts the 2019 California Electrical Code, as the City's Electrical Code in Title 8, Chapter 10.
106.1 Plan Check Requirements. ... Only after the plans have been approved may the applicant apply for an electrical permit for such work. ... 107.1 Electrical Permit Required. No person shall erect, alter, install, repair, move, improve, remove, connect or convert, or cause the same to be done, any electrical equipment without first obtaining an electrical permit from the building official. ... 107.2 Work Exempted from Electrical Permit. An Electrical Permit shall not be required for the following: (1) Minor repair work such as the replacement of lamps, switches, receptacle devices and sockets which were previously permitted and inspected under a valid electrical permit; ... (3) Repair or replacement of overcurrent devices; ... (8) Temporary decorative lighting which is not installed for more than 90 days;
Full Breakdown
Section 107.1 of the Huntington Park Electrical Code is the permit trigger. It covers erecting, altering, installing, repairing, moving, improving, removing, connecting or converting any electrical equipment, and the permit comes from the building official. Issuing a permit without first requiring plan review does not stop the building official from asking for plans later to verify that the finished work complies with the Code and all relevant laws.
Plan check comes first when the building official requires it, and only after the plans are approved can the applicant apply for the permit. Separate Electrical Code plan review is required for installations such as equipment rated at 400 amperes or larger, a subpanel, switchboard or motor control center rated at 400 amperes or larger, a motor rated more than 10 HP, storage batteries, equipment rated above 600V, lighting fixtures weighing more than 300 pounds, and any illuminated sign. Plans must bear the seal, signature and number of an electrical engineer when the California Business and Professions Code requires one. The first sheet of each set shows the street address of the work and the name, address and telephone number of the owner and everyone involved in the design.
Section 107.2 lists the work that needs no permit: replacing lamps, switches, receptacle devices and sockets that were previously permitted and inspected, repair or replacement of overcurrent devices, wiring operating at less than 25 volts that cannot supply more than 50 watts, and temporary decorative lighting installed for no more than 90 days. An exemption never authorizes work that breaks another law or ordinance.
Section 8-10.02 adopts Title 27 of the Los Angeles County Code, the 2019 Los Angeles County Electrical Code, by reference under Government Code Sections 50022.1 through 50022.10. A copy stays on file with the Building Official in the Building and Safety Division. Administration follows Section 8-1.01, Building Code Administration. The chapter does not reach public utilities, street lighting or traffic signals located primarily in a public way.
Violations & Fines
Under Section 8-10.04, every prohibited act or failure to perform a required act under the Electrical Code is a misdemeanor or an infraction. Where the Code is silent, the City Attorney picks either charge. Anyone who causes, aids, abets or conceals a violation is guilty of violating the Code. The City can also sue civilly, and any condition in violation is a public nuisance that the City can summarily abate.
Frequently Asked Questions
Do I need a permit to replace a light switch in the City of Huntington Park?
Which electrical code applies in Huntington Park, California?
When does an electrical job need separate plan review?
What happens if someone skips the electrical permit?
Sources & Official References
Other rules in Huntington Park
California rules heatmap·Compare Huntington Park to another location·View the California building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Electrical Permits in Nearby Cities
How other cities in Los Angeles County handle electrical permits.