Lakeville, MN Building Safety: Electrical Permits (2026)
Key Facts
- Permit trigger
- Any new, altered or repaired electrical work
- New-structure installer
- State-licensed electrical contractor only
- Existing-structure installer
- Licensed contractor or resident owner
- Pre-permit requirement
- Fee plus valid state contractor certificate
- Concealment rule
- Rough-in inspection before covering wiring
- Enforcement
- City electrical inspector, licensed electrician
Summary
In the City of Lakeville, Minnesota, City Code section 9-6-6 requires an electrical permit for every installation, alteration, addition or repair of electrical work for light, heat and power in the city. New-structure work must go through a state-licensed electrical contractor, while existing-structure work can also be done by the resident owner, and every permit carries a fee plus a state contractor's certificate requirement.
9-6-6: PERMITS AND INSPECTIONS: ... A. Permit Required: An electrical permit is required for each installation, alteration, addition or repair of electrical work for light, heat and power within the limits of the city. Permits for the installation of electrical work in new structures shall only be issued to electrical contractors duly licensed by the state. Permits for the installation, alteration, addition or repair of electrical work in existing structures shall only be issued to electrical contractors duly licensed by the state or to resident owners of property where the work is to be done. ... D. Fee: ... Before any permit is granted for the installation or alteration of electrical equipment, the person making application for such permit shall pay the city a fee in such amount as specified in the adopted schedule of fees and furnish proof of a valid state contractor's certificate. ... ... F. Concealment: All electrical installations which involve the concealment of wiring or equipment shall have a "rough-in" inspection prior to concealment, wherein the inspector shall be duly notified in advance, excluding Saturday, Sunday and holidays.
Full Breakdown
City Code section 9-6-6 implements Chapter 9-6, which the city adopted to apply the Minnesota State Building Code and Minnesota Rules chapter 1315, the National Electrical Code, within Lakeville. Subsection A requires an electrical permit for each installation, alteration, addition or repair of electrical work for light, heat and power in the city; permits for new structures may be issued only to electrical contractors licensed by the state, while permits for existing structures can go to a licensed contractor or to the resident owner of the property where the work is being done.
Subsection D requires a fee, set by the adopted fee schedule, before any permit is granted, and the applicant must furnish proof of a valid state contractor's certificate. The application itself, under subsection E, must be made in writing and accompanied by plans, specifications and schedules sufficient to show the installation will conform to legal requirements, with the inspection fee submitted alongside it; a permit issues once the applicant has complied with the chapter. Subsection F requires a rough-in inspection before any wiring or equipment is concealed, with the inspector notified in advance excluding weekends and holidays.
The electrical inspector position, created under section 9-6-2, is filled by a licensed master or journeyman electrician who reviews applications, grants permits, performs inspections, and can order equipment disconnected if it is found unsafe. A narrow exception in subsection B removes the permit requirement for equipment owned and operated by a public service corporation acting as a utility, though that equipment must still meet national electrical safety code standards.
Violations & Fines
Connecting electricity to equipment for which a permit is required, or that has been ordered disconnected, is unlawful under section 9-6-5. The electrical inspector can order a utility to disconnect service to any installation found unsafe or installed contrary to the adopted code, and can require disconnection within 15 days of written notice of a defect, or immediately in an emergency.
Frequently Asked Questions
Can I do my own electrical work in Lakeville?
What do I need before an electrical permit is issued in Lakeville?
Do I need an inspection before covering up new wiring?
Sources & Official References
Other rules in Lakeville
Compare Lakeville to another location·View the Minnesota building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.