Key Facts
- Licensing authority
- Electrical administrative board, Sec. 7-18
- State law basis
- MCL 338.881 et seq., licensed contractors
- Electrical code source
- State Construction Code adopted under Sec. 7-16
- Permit enforcement
- Building official and designated inspectors, Sec. 7-17
- Default penalty
- Up to 90 days jail, $500 fine (Sec. 1-11)
Summary
Electrical work inside the City of Novi is licensed through the electrical administrative board, not city hall directly. Section 7-18 transfers that licensing authority to the board under state law, while the electrical code itself reaches Novi as part of the state construction code the city adopted under Section 7-16.
Pursuant to the laws of the state, authority for electrical licensing is hereby transferred to the electrical administrative board. ... State Law reference— Licensed contractors, MCL 338.881 et seq.
Full Breakdown
Section 7-18 of the Novi Code is short but specific: it transfers authority for electrical licensing to the electrical administrative board, acting pursuant to state law rather than a city-run licensing office. The accompanying state law reference in the Code points to MCL 338.881 et seq., the state statute governing licensed contractors, confirming that Novi's electrical licensing structure runs on that state framework rather than a locally invented one. The electrical code that a Novi permit actually gets measured against is not written into this chapter directly.
Section 7-16 folds an "electrical" code into the list of codes promulgated as the State Construction Code under Section 4 of the Stille-DeRossett-Hale Act, so Novi enforces whichever electrical code edition the state has adopted as part of that construction code, rather than printing its own electrical chapter. Enforcement on the ground falls to the same enforcing agency named in Section 7-17: the building official and whichever inspectors, including electrical inspectors, that official designates. A contractor pulling an electrical permit in Novi is therefore dealing with two linked but separate systems: the electrical administrative board controls who is licensed to do the work, while the building official's office controls the permit and inspection of the work itself once a licensed electrician is on the job.
Violations & Fines
Electrical work performed without the license the electrical administrative board controls under Section 7-18, or without the permit the building official issues under the adopted state construction code, defaults to Section 1-11's general penalty: a misdemeanor punishable by up to 90 days in jail and a $500 fine, or, where a section designates it a municipal civil infraction, a $200 first-offense civil fine rising to $500 for a repeat.
Frequently Asked Questions
Who licenses electricians in the City of Novi?
Does Novi have its own electrical code, or does it use the state's?
Who inspects electrical permits once the work starts?
Sources & Official References
Other rules in Novi
Compare Novi to another location·View the Michigan building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.