Key Facts
- Base fee
- $75 for one to 50 receptacles or fixtures
- Each additional 25 fixtures
- $20
- EV charger
- $100 residential, $150 commercial, per charger
- Plan review
- 25% of the construction permit charge, non-refundable
- Permit renewal
- 10% of original fee, minimum $75
- Appeal deadline
- 15 days to the Union County Board of Construction Appeals
Summary
In the City of Plainfield, New Jersey, electrical work is priced under the Electrical Subcode fee schedule in § 2:10-6C, which starts at $75 for one to 50 receptacles or fixtures and adds $20 for each additional 25. The Department of Economic Development, through its Electrical Subcode Official, runs the local State Uniform Construction Code Enforcing Agency.
§ 2:10-6C. Fee schedule. ... (a) Subcode fees shall be as follows: ... (3) Electrical Subcode fees shall be: (A) For from one to 50 receptacles or fixtures, the fee shall be $75; for each additional 25 receptacles or fixtures, the fee shall be $20. Receptacles or fixtures shall include; lighting outlets, wall switches, fluorescent fixtures, convenience receptacles or similar fixtures, and motors or devices of less than one horsepower or one kilowatt. (B) For each motor or electrical device greater than one horsepower and less than or equal to 10 horsepower; and for transformers and generators greater than one kilowatt and less than or equal to 10 kilowatts, the fees shall be $75. ... (D) For each motor or electrical device greater than 50 horsepower and less than or equal to 100 horsepower the fee shall be $125; for each service panel, service entrance or subpanel greater than 125 amperes and less than or equal to 1000 amperes, the fee shall be $125. (E) For each motor or electrical device greater than 100 horsepower; for each service entrance or subpanel greater than 1,000 amperes; and for each transformer or generator greater than 112.5 kilowatts, the fee shall be $500.
Full Breakdown
The Plainfield City Council established the local State Uniform Construction Code Enforcing Agency in § 2:10-6A and named it the Department of Economic Development. The agency consists of a Director, a Construction Official, and separate Building, Plumbing, Electrical and Fire Protection Subcode Officials. The code requires that the public have the right to do business with the enforcing agency at one office location except for emergencies and unforeseen or unavoidable circumstances. Section 2:10-6C, amended 4-8-2024 by Ord. No. MC 2024-15, sets what each subcode costs.
The Electrical Subcode schedule is built on counts and ratings. One to 50 receptacles or fixtures cost $75, and each additional 25 cost $20. A motor or electrical device above one horsepower and up to 10 horsepower costs $75, and so do transformers and generators above one kilowatt and up to 10 kilowatts. Devices above 10 horsepower and up to 50 horsepower are $75 as well, as is each service panel, service entrance or subpanel of 100 amperes or less. Between 50 and 100 horsepower the fee is $125, and service panels above 125 amperes and up to 1000 amperes also cost $125. Anything above 100 horsepower, any service entrance or subpanel above 1,000 amperes, and any transformer or generator above 112.5 kilowatts costs $500. For counting, all motors except those in plug-in appliances are counted, including control equipment, generators, transformers and all heating, cooking or other devices consuming or generating electrical current.
Specific installations carry flat fees. An HVAC system installation or replacement is $75 for each system, an energy management lighting or motor control panel is $100 each, and electric vehicle charging stations are $100 per charger for residential systems and $150 per charger for commercial systems. An annual public pool inspection is $250. Plan review is 25% of the amount charged for the construction permit, paid before the plans are reviewed, credited toward the permit total and non-refundable. A permit renewal is 10% of the original construction permit fee with a minimum of $75.
Violations & Fines
Section 2:10-6C prints fees, not criminal penalties. The charges that bite are procedural: plan review fees are non-refundable, an application for a variation from the applicable codes costs $125 per affected subcode, and a change of contractor carries a $25 administrative fee per update for each subcode. Decisions of the enforcing agency are appealed within 15 days to the Union County Board of Construction Appeals under § 2:10-6B.
Frequently Asked Questions
How much is a basic electrical permit in Plainfield?
Who enforces electrical permits in the City of Plainfield?
What does an electric vehicle charger permit cost in Plainfield?
Can I appeal an electrical inspection decision in Plainfield?
Sources & Official References
Other rules in Plainfield
Compare Plainfield to another location·View the New Jersey building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Electrical Permits in Nearby Cities
How other cities in Union County handle electrical permits.