Roseville, MN Building Safety: Electrical Permits (2026)
Key Facts
- Adopted code
- Electrical code as a section of the MSBC
- Fee authority
- Current electrical inspection services contract approved by the City Council
- Residential minimum fee (2026)
- $60.00, no refunds
- Single-family under 200 amps (2026)
- $225.00 plus $1.00 State surcharge
- Re-inspection fee (2026)
- $60.00 in addition to others
- Completion notice
- Five working days to the designated building official
Summary
Roseville makes the electrical code an adopted section of the Minnesota State Building Code. Electrical work fees follow the most current electrical inspection services contract approved by the City Council, and the city fee schedule's 2026 electrical table starts residential permits at a $60.00 minimum fee with no refunds.
The electrical code is an adopted section of the MSBC. Fees for electrical work shall be as established in the most current electrical inspection services contract approved by the city council.
Official source re-checked November 3, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 2).
Full Breakdown
Section 903.01 is short: the electrical code is an adopted section of the MSBC, and fees for electrical work are those established in the most current electrical inspection services contract approved by the city council. Section 901.07(a) adds that permits are required as specified in the MSBC, so the state code decides which electrical jobs need one, while Roseville decides what they cost.
The city fee schedule in Appendix A, section 314.054, Electrical Permit Fees, prints a 2026 Amount column. Under Residential Fees (Single Family Homes, Apartments, and Condominiums), the minimum fee is $60.00 and no refunds are available. Changes for services run $75.00 for 0 to 300 amp. The table lists a single-family dwelling or townhouse under 200 amps at $225.00 plus a $1.00 State surcharge, up to 25 circuits, with additional circuits at $12.00 each. Other printed lines include a swimming pool (up to two inspections) at $120.00 plus circuits at $12.00 each, additions, remodels and basement additions at $120.00 for up to ten circuits and two inspections, a residential panel replacement at $125.00, solar of 0 to 5 kw at $100.00, and a re-inspection fee of $60.00 in addition to others.
Other building-title rules attach. Section 901.06 collects a state surcharge on all permits for work governed by Title 9. Under section 901.11 the permit holder must notify the designated building official within five working days after the work is completed. Under section 901.12 a permit becomes invalid at the end of 180 days unless work has started and expires after work is abandoned or suspended for 180 days.
Violations & Fines
Section 102.01(a) makes violating the city Code a misdemeanor unless the Code provides otherwise: a fine not to exceed $1,000.00, imprisonment not to exceed 90 days, or both, with costs of prosecution added. Section 901.13 states that the issuance of a permit is no defense to a violation of the title or other regulation.
Frequently Asked Questions
Which electrical code does Roseville use?
How does Roseville set electrical permit fees?
What does a single-family electrical permit cost?
Is there a fee for a failed inspection?
Sources & Official References
Other rules in Roseville
Compare Roseville to another location·View the Minnesota building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.