Roseville, MN Building Safety: Building Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified November 2026

Key Facts

Fences and walls
Permit required over four feet tall, new and replacement
Other listed items
Driveways, drain tile, sheds, permanent and temporary signs
Permit lapse
180 days without work starting; 180 days after work stops
Fire inspection add-on
Eight percent of the building permit fee
Construction deposit trigger
More than 50 percent of existing structure's cost evaluation
Issuing official
Designated building official

Summary

Roseville requires permits wherever the Minnesota State Building Code says so, and adds its own permit list: fences and walls over four feet tall, driveways, drain tile, sheds, and signs. Moving a building and demolishing a building or in-ground pool need permits too. The designated building official processes applications and issues the permits.

(a) Permits shall be required as specified in the MSBC. (b) Permits shall be required for the following to verify compliance with the city Code. Fees, based on valuation, shall be as established in the most current city fee schedule. (1) Fences over four feet tall (new and replacement). (2) Walls over four feet tall (new and replacement). (3) Driveways (new and replacement). (4) Drain tile installations (new and replacement). (5) Sheds. (6) Permanent and temporary signage. (c) Moving of dwellings or buildings. (1) Permit required. The applicant for a permit to move a building or dwelling shall pay a fee as established in the city fee schedule. ... (d) Demolition permits. The applicant for a permit to demolish or wreck a building or in-ground pool shall pay a fee as established in the city fee schedule.

View official code

Official source re-checked November 3, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 2).

Full Breakdown

Section 901.07(a) ties Roseville's permit trigger to the Minnesota State Building Code (MSBC), so any work the MSBC says needs a permit needs one in the city. Subsection (b) adds a city list: fences over four feet tall, walls over four feet tall, driveways and drain tile installations (new and replacement in each case), sheds, and permanent and temporary signage. The stated purpose is to verify compliance with the city Code, and fees are based on valuation under the current city fee schedule. Moving a dwelling or building takes a permit under subsection (c); inspection of buildings outside the city limits is charged at an hourly rate plus a mileage charge for city vehicles. Demolishing a building or an in-ground pool takes a permit under subsection (d). Further subsections cover gas piping and HVAC equipment (e), plumbing (f), excavation, grading and surfacing (g), signs (h), special events and temporary tents (j), and a minimum fee for any permit (k). When a fee depends on market value, the designated building official ascertains the value.

Around the permit itself, section 901.02 has the designated building official receive and process applications, inspect premises, ascertain compliance and issue permits. Under section 901.05 the fee is the fee-schedule amount plus an amount equal to eight percent of the building permit fee to defray the cost of fire safety inspections, and section 901.06 adds the state surcharge. Section 901.08 bars a construction permit until the finance director certifies the lot has been assessed for contiguous public roads, curbs or sidewalks, or the applicant pays the assessable share. Section 901.09 requires a cash deposit when the building official reasonably finds a project involves more than 50 percent of the cost evaluation of the existing structure. Under section 901.12 a permit becomes invalid at the end of 180 days unless work has started, and it expires after work is abandoned or suspended for 180 days. Work in the public right-of-way needs its own permit under section 901.10.

Violations & Fines

Violating Title 9 or any other provision of the city Code is a misdemeanor under section 102.01(a) unless the Code provides otherwise: a fine not to exceed $1,000.00, imprisonment not to exceed 90 days, or both, with costs of prosecution added. Section 901.13 removes one defense: the fact that a permit was issued is no defense to a charge of violating the building title or another regulation.

Frequently Asked Questions

Do I need a permit for a shed in Roseville?
Yes. Section 901.07(b)(5) lists sheds among the items that require a permit, and unlike fences and walls it prints no height threshold. Fees are based on valuation under the current city fee schedule. Zoning placement standards for accessory structures are separate and sit in Title 10 of the city Code.
How tall can a fence be before Roseville requires a permit?
Section 901.07(b)(1) requires a permit for fences over four feet tall, both new and replacement. Section 901.07(b)(2) sets the same four-foot trigger for walls. Both permits are issued to verify compliance with the city Code, with fees based on valuation.
How long is a Roseville building permit valid?
Under section 901.12, a permit becomes invalid at the end of 180 days from issuance unless the work has started. The designated building official can extend that period if the applicant applies in writing before the permit expires. A permit also expires once work is abandoned or suspended for 180 days.
Is anything added to the building permit fee?
Yes. Section 901.05 adds an amount equal to eight percent of the building permit fee to defray the cost of fire safety inspections, and section 901.06 collects the state surcharge in accordance with state law on all permits issued for work governed by Title 9.
Do I need a permit to demolish a building or pool?
Yes. Section 901.07(d) requires a demolition permit to demolish or wreck a building or an in-ground pool, with the fee set in the city fee schedule. Moving a dwelling or building is covered separately by subsection (c).

Sources & Official References

Other rules in Roseville

All Roseville rules

Compare Roseville to another location·View the Minnesota building safety overview

Get notified when Building Permits in Roseville, MN changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.