Key Facts

Trigger
New lots; expansions or improvements over 25 percent
Small lots
29 or fewer spaces: charging is optional
Future-ready EVSE
Minimum ten percent of required spaces
Gas stations
At least one Level 2 or greater EVCS
Cost cap for reduction
Over five percent of total project cost
Residential stations
Designated private restricted use only

Summary

Roseville requires electric vehicle charging stations in new parking areas and in existing lots that add more than 25 percent more spaces or have more than 25 percent of the lot improved, under Table 1013.04-2. New nonresidential and multiple-family lots must also install EVSE capacity for a minimum of ten percent of required spaces.

(d) Electric vehicle charging standards. ... (2) Minimum number of required electric vehicle charging stations (EVCS). a. All new parking areas, existing parking areas expanding by more than 25 percent additional parking spaces, and existing parking areas improving more than 25 percent of the parking area are subject to the standards of Table 1013.04-2. ... d. In addition to the number of required EVCS, the following accommodations shall be required for the anticipated future growth in market demand for electric vehicles: 1. New nonresidential and multiple-family residential land uses (five or more units per building). All new parking areas shall provide electric vehicle supply equipment (EVSE) with the electrical capacity necessary to accommodate the future hardwire installation of EVCS as Level 2 or greater for a minimum of ten percent of required parking spaces. ... (3) Reductions to EVSE and EVCS requirements. When the cost of meeting the requirements of this section would exceed five percent of the total project cost, the property owner or applicant may request a reduction in the requirements and submit cost estimates for city consideration.

View official code

Official source re-checked November 3, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 2).

Full Breakdown

Section 1013.04(d) of the Roseville City Code sets the electric vehicle charging standards for off-street parking. Table 1013.04-2 applies to all new parking areas, to existing parking areas expanding by more than 25 percent additional parking spaces, and to existing parking areas improving more than 25 percent of the parking area. Charging is optional for lots with 29 or fewer spaces. For new lots of 30 to 49 spaces, multiple-family residential (five or more units) must provide 5 percent of required spaces as Level 1 or greater, and nonresidential uses must provide 2 parking spaces as Level 2 or greater, with at least one accessible in each case. At 50 or more spaces, multiple-family lots must provide 10 percent of required spaces as Level 1 or greater plus one guest space as Level 2 or greater, and nonresidential lots must provide 5 percent as Level 2 or greater. Percentage results below one round up to one, and fractions of at least one-half round up.

All new motor fuel sales (gas stations) must install at least one EVCS as Level 2 or greater. Every new nonresidential or multiple-family parking area must also provide EVSE with the electrical capacity to accommodate later hardwire installation of Level 2 or greater stations for a minimum of ten percent of required parking spaces. The city council can revise these numbers upward or downward when it acts on a conditional use permit or planned unit development.

If meeting the rules would cost more than five percent of the total project cost, the owner can submit cost estimates and request a reduction. Where council approval of the project is not required, the community development department can approve a reduction administratively.

Stations are permitted in every zoning district when accessory to the primary use, and stations at residential uses are designated private restricted use only. One- to four-family homes must place a station in the garage or on the exterior wall of the home or garage next to a parking space. For multifamily and nonresidential sites, public-use stations must be easily seen, sited in desirable and convenient parking locations, and operational during normal business hours. Site lighting is required unless charging is for daytime purposes only, and equipment must carry a phone number or other contact information for reporting problems.

Violations & Fines

Section 1013.04(d) prints no fine of its own. Enforcement runs through permitting: Section 1013.02 bars a building permit or certificate of occupancy for a new building, an enlargement, or a change of use unless off-street parking spaces, loading bays, and bicycle parking are provided in accordance with the Code. Reduction requests go to the community development department or, where council approval is needed, to the city council.

Frequently Asked Questions

Do I have to add EV chargers if I expand a parking lot in Roseville?
Yes, once the expansion adds more than 25 percent additional parking spaces, or the work improves more than 25 percent of the lot. Charging stations are then required at the new-lot quantities in Table 1013.04-2, prorated to the spaces in the area of expansion or improvement for multiple-family sites.
Are small parking lots exempt from EV charging rules in Roseville?
Lots with 29 or fewer spaces have optional charging under Table 1013.04-2. At 30 to 49 spaces a nonresidential lot needs 2 Level 2 or greater spaces, and from 50 spaces up a nonresidential lot needs 5 percent of required spaces as Level 2 or greater.
Can the EV charging requirement be reduced?
Yes. When meeting the rules would cost more than five percent of total project cost, the owner can submit cost estimates and request a reduction. If city council approval is not required for the project, the community development department can approve the reduction administratively.
Can I install a home charger at my single-family house in Roseville?
Level 1, Level 2, and DC stations are permitted in every zoning district when accessory to the primary use. At one- to four-family dwellings the station must be in a garage or on the exterior wall of the home or garage next to a parking space, and it is designated private restricted use only.

Sources & Official References

Other rules in Roseville

All Roseville rules

Compare Roseville to another location·View the Minnesota parking rules overview

Get notified when EV Charging in Roseville, MN changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

EV Charging in Nearby Cities

How other cities in this county handle ev charging.

Saint Paul, MN
Some Restrictions