Roseville, MN Environmental Rules: Flood Elevation Requirements (2026)
Key Facts
- Freeboard
- One foot above the regional flood elevation
- Regional flood
- Same as base flood, one percent annual chance, 100-year
- Lowest floor in flood fringe
- At or above the regulatory flood protection elevation
- Fill extent
- At least 15 feet beyond the structure
- Floodproofed accessory structures
- Up to 500 square feet at largest projection
- Residential basements
- Not allowed below the elevation
Summary
Roseville sets the regulatory flood protection elevation at no lower than one foot above the elevation of the regional flood, plus any increases in flood elevation caused by floodway encroachments. In the flood fringe, the lowest floor, including a basement floor, must be at or above that elevation.
(c) Regulatory flood protection elevation. The regulatory flood protection elevation shall be an elevation no lower than one foot above the elevation of the regional flood plus any increases in flood elevation caused by encroachments on the floodplain that result from designation of a floodway. ... Lowest floor means the lowest floor of the lowest enclosed area (including basement). An unfinished or flood-resistant enclosure used solely for parking of vehicles, building access, or storage in an area other than a basement area is not considered a building's lowest floor. ... Regional flood means a flood which is representative of large floods known to have occurred generally in the state and reasonably characteristic of what can be expected to occur on an average frequency in the magnitude of the 100-year recurrence interval.
Official source re-checked November 3, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 2).
Full Breakdown
Section 1015.02(c) of the Roseville City Code defines the regulatory flood protection elevation as an elevation no lower than one foot above the elevation of the regional flood plus any increases in flood elevation caused by encroachments on the floodplain that result from designation of a floodway. That one foot is the freeboard. The definitions in subsection (h) tie the regional flood to a 100-year recurrence interval and make it synonymous with the base flood, the one percent annual chance flood, and the 100-year flood elevation.
The lowest floor definition decides what must clear the elevation. It is the lowest floor of the lowest enclosed area, including a basement, but an unfinished or flood-resistant enclosure used solely for parking of vehicles, building access, or storage in an area other than a basement is not counted.
Section 1015.05(b) applies the elevation in the flood fringe district. All structures, including accessory structures, must be elevated on fill so the lowest floor, including basement floor, is at or above the regulatory flood protection elevation. The finished fill elevation can be no lower than one foot below that elevation, and the fill must extend at that elevation at least 15 feet beyond the outside limits of the structure. Accessory structures that do not exceed 500 square feet at their largest projection can instead be floodproofed, and storage of materials or equipment must be elevated on fill to the regulatory flood protection elevation. Residential basement construction is not allowed below it. Nonresidential basements below it are allowed only if structurally dry floodproofed to the FP-1 or FP-2 classification in the state building code.
Where the flood maps show Zone A without a determined elevation, Section 1015.06 makes the applicant furnish the information needed to establish the one percent annual chance flood elevation under approved FEMA methods, following Minn. Rules 6120.5000 to 6120.6200 and 44 CFR 65. Section 1015.03(b)(2) requires as-built elevations for elevated or floodproofed structures to be certified by ground surveys.
Violations & Fines
A violation of Chapter 1015, including building below the required elevation, is a misdemeanor under Section 1015.12. The zoning administrator can halt construction until a proper permit is granted, order corrective action within a specified time, or require an after-the-fact permit application within a period not to exceed 30 days. Each additional day of noncompliance is a separate violation.
Frequently Asked Questions
How much freeboard does Roseville require above the base flood?
Can I have a basement in a Roseville flood fringe area?
How far must elevation fill extend around a Roseville building?
What if my property is in Zone A with no published elevation?
Sources & Official References
Other rules in Roseville
Compare Roseville to another location·View the Minnesota environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Flood Elevation Requirements in Nearby Cities
How other cities in this county handle flood elevation requirements.