Bothell, WA Building Safety: Building Inspections (2026)
Key Facts
- Inspection authority
- Building official, under § 20.02.160
- Work must stay
- Accessible and exposed until approved
- Rough-in rule
- No utility connections until rough-in approved
- Roof rule
- No roof coverings until sheathing inspection approved
- Who requests inspections
- Permit holder or authorized agent, per § 20.02.195
- Covered-work cost
- Three times the inspector hourly rate
Summary
In the City of Bothell, Washington, work that needs a permit must stay exposed until the building official approves it. Bothell Municipal Code § 20.02.160 sets the inspection sequence, from footing and foundation through framing, and § 20.02.200 bars work beyond each stage without approval.
A. Construction or work for which a permit is required shall be subject to inspection by the building official and such construction or work shall remain accessible and exposed for inspection purposes until approved. ... D. The building official, upon notification, shall make the following inspections: 1. Footing and Foundation Inspection. Footing and foundation inspections shall be made after poles or piers are set or trenches or basement areas are excavated and all required hold-down anchor bolts, hold-down straps, any forms erected, and any required reinforcing steel is in place and supported. ... 9. Frame Inspection. Framing inspections shall be made after the roof deck, wall sheathing, all framing, fire blocking and bracing are in place and pipes, chimneys and vents to be concealed are complete and the rough electrical, plumbing, fire suppression piping, heating wires, pipes and ducts are approved and the building is substantially dried in.
Full Breakdown
Bothell Municipal Code § 20.02.160(A) puts all permitted construction under inspection by the building official and requires the work to stay accessible and exposed until approved. The permit applicant carries that duty, and neither the building official nor the City of Bothell pays to remove or replace material needed to allow inspection. An approval never counts as approval of a violation of the code.
Subsection D lists the stages, each made upon notification. The footing and foundation inspection comes after poles or piers are set or trenches or basement areas are excavated, with hold-down anchor bolts, straps, forms and reinforcing steel in place. The concrete slab and under-floor inspection comes before any concrete is placed or floor sheathing installed. In flood hazard areas the lowest floor elevation certificate goes to the building official before further vertical construction. Exterior wall sheathing and roof sheathing are inspected after framing is complete and before covering, and no roof coverings go on until the roof inspection is approved. The rough-in inspection covers mechanical, gas piping, plumbing and electrical work, and no connections to primary utilities are allowed until it is approved. Flashing and weather barrier, lath and gypsum board, and fire- and smoke-resistant penetrations are each inspected before concealment. The frame inspection happens once the roof deck, wall sheathing, fire blocking and bracing are in place and the building is substantially dried in.
The permit holder must tell the building official when work is ready (§ 20.02.195). Under § 20.02.200, work cannot go past the point of each inspection without approval, and failed portions must be corrected and stay uncovered until authorized. A final inspection follows completion of all permitted work (§ 20.02.185), and a certificate of occupancy comes after (§ 20.02.205).
Violations & Fines
A re-inspection fee can be assessed under § 20.02.170 when work is not complete, earlier corrections were not made, duplicate inspections are requested, the approved plans and permit are not on site, or the building is not accessible. The city then provides no further inspection until the fees are paid. Under § 20.02.161, work continued past approval or covered without inspection costs full recovery at three times the current hourly rate for a city inspector.
Frequently Asked Questions
What inspections does the City of Bothell require during construction?
Who has to call for a Bothell inspection?
Can I cover up work before the inspector arrives?
What triggers a re-inspection fee in Bothell?
Sources & Official References
Other rules in Bothell
Compare Bothell to another location·View the Washington building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Building Inspections in Nearby Cities
How other cities in King County handle building inspections.