Skip to main content
CityRuleLookup

Bothell, WA Building Safety: Building Inspections (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified October 2026

Key Facts

Inspection authority
Building official, under § 20.02.160
Work must stay
Accessible and exposed until approved
Rough-in rule
No utility connections until rough-in approved
Roof rule
No roof coverings until sheathing inspection approved
Who requests inspections
Permit holder or authorized agent, per § 20.02.195
Covered-work cost
Three times the inspector hourly rate

Summary

In the City of Bothell, Washington, work that needs a permit must stay exposed until the building official approves it. Bothell Municipal Code § 20.02.160 sets the inspection sequence, from footing and foundation through framing, and § 20.02.200 bars work beyond each stage without approval.

A. Construction or work for which a permit is required shall be subject to inspection by the building official and such construction or work shall remain accessible and exposed for inspection purposes until approved. ... D. The building official, upon notification, shall make the following inspections: 1. Footing and Foundation Inspection. Footing and foundation inspections shall be made after poles or piers are set or trenches or basement areas are excavated and all required hold-down anchor bolts, hold-down straps, any forms erected, and any required reinforcing steel is in place and supported. ... 9. Frame Inspection. Framing inspections shall be made after the roof deck, wall sheathing, all framing, fire blocking and bracing are in place and pipes, chimneys and vents to be concealed are complete and the rough electrical, plumbing, fire suppression piping, heating wires, pipes and ducts are approved and the building is substantially dried in.

Full Breakdown

Bothell Municipal Code § 20.02.160(A) puts all permitted construction under inspection by the building official and requires the work to stay accessible and exposed until approved. The permit applicant carries that duty, and neither the building official nor the City of Bothell pays to remove or replace material needed to allow inspection. An approval never counts as approval of a violation of the code.

Subsection D lists the stages, each made upon notification. The footing and foundation inspection comes after poles or piers are set or trenches or basement areas are excavated, with hold-down anchor bolts, straps, forms and reinforcing steel in place. The concrete slab and under-floor inspection comes before any concrete is placed or floor sheathing installed. In flood hazard areas the lowest floor elevation certificate goes to the building official before further vertical construction. Exterior wall sheathing and roof sheathing are inspected after framing is complete and before covering, and no roof coverings go on until the roof inspection is approved. The rough-in inspection covers mechanical, gas piping, plumbing and electrical work, and no connections to primary utilities are allowed until it is approved. Flashing and weather barrier, lath and gypsum board, and fire- and smoke-resistant penetrations are each inspected before concealment. The frame inspection happens once the roof deck, wall sheathing, fire blocking and bracing are in place and the building is substantially dried in.

The permit holder must tell the building official when work is ready (§ 20.02.195). Under § 20.02.200, work cannot go past the point of each inspection without approval, and failed portions must be corrected and stay uncovered until authorized. A final inspection follows completion of all permitted work (§ 20.02.185), and a certificate of occupancy comes after (§ 20.02.205).

Violations & Fines

A re-inspection fee can be assessed under § 20.02.170 when work is not complete, earlier corrections were not made, duplicate inspections are requested, the approved plans and permit are not on site, or the building is not accessible. The city then provides no further inspection until the fees are paid. Under § 20.02.161, work continued past approval or covered without inspection costs full recovery at three times the current hourly rate for a city inspector.

Frequently Asked Questions

What inspections does the City of Bothell require during construction?
Section 20.02.160(D) lists footing and foundation, concrete slab and under-floor, lowest floor elevation in flood hazard areas, exterior wall sheathing, roof sheathing, rough-in for mechanical, gas, plumbing and electrical, flashing and weather barrier, lath and gypsum board, framing, and fire- and smoke-resistant penetrations. A final inspection follows when all permitted work is complete.
Who has to call for a Bothell inspection?
Section 20.02.195 makes the holder of the building permit or the holder's authorized agent responsible for notifying the building official when work is ready. The permit holder must also provide access and the means for each required inspection, and manufacturer's installation instructions must be on the job site at the time of inspection.
Can I cover up work before the inspector arrives?
No. Section 20.02.200 says work cannot proceed past the point of each inspection without the building official's approval, and any portion that fails must be corrected and left uncovered until authorized. Covering work without inspection on a permitted project carries full cost recovery at three times the current hourly inspector rate under § 20.02.161.
What triggers a re-inspection fee in Bothell?
Section 20.02.170 allows a fee for each inspection or re-inspection when the requested work is not complete, earlier corrections were not made, duplicate inspections are requested, the approved plans and permit are not on site, or the building is not accessible. No further inspection is provided until the assessed fees are paid.

Sources & Official References

Other rules in Bothell

All Bothell rules

Compare Bothell to another location·View the Washington building safety overview

Get notified when Building Inspections in Bothell, WA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Inspections in Nearby Cities

How other cities in King County handle building inspections.

Auburn, WA
Some Restrictions
Bellevue, WA
Some Restrictions
Kirkland, WA
Some Restrictions
Renton, WA
Some Restrictions