Key Facts

Governing section
Clovis Municipal Code § 8.1.01.1(f)
Inspecting authority
City of Clovis Building Official
Required stages
Foundation, slab, frame, lath/wallboard, final
Permit expiration trigger
180 days without a passed inspection
Violation classification
Misdemeanor, separate offense per day

Summary

Clovis Municipal Code Section 8.1.01.1(f) rewrites the Building Code's Section 305.5 to require the building official's approval before covering reinforcing steel, structural framing, or fire-resistive joint protection. It fixes six mandatory inspection stages, from the foundation through the final walk-through, that every permitted project must pass before work can proceed or a certificate of occupancy issues.

305.5 Required Building Inspections. Reinforcing steel or structural framework or a part of a building or structure shall not be covered or concealed without first obtaining the approval of the building official. Protection of joints and penetrations in fire-resistive assemblies shall not be concealed from view until inspected and approved. The building official, upon notification, shall make the following inspections: 1. Foundation inspection. To be made after excavations for footings are complete and required reinforcing steel is in place... 2. Concrete slab or under-floor inspection. To be made after in-slab or under-floor equipment, conduit, and piping are in place but before any concrete is placed or floor sheathing installed... 3. Frame inspection. To be made after the roof, framing, fire blocking and bracing are in place and all pipes, chimneys and vents are complete... 4. Lath and/or wallboard inspection. To be made after lathing and wallboard is in place but before plaster is applied or wallboard joints are taped and finished. 6. Final inspection. To be made after finish grading and the building is completed and ready for occupancy.

Full Breakdown

1 to fit the City's Building Division processes. 5, Required Building Inspections, to bar covering or concealing reinforcing steel or structural framework, and to bar concealing fire-resistive joint and penetration protection, until the building official has approved the work. On notification from the permit holder, the building official must perform six inspections in sequence: a foundation inspection after excavation and reinforcing steel placement (with forms in place for concrete foundations); a concrete slab or under-floor inspection before concrete or subfloor sheathing covers in-slab equipment and piping; a frame inspection once roof framing, fire blocking, bracing, and rough electrical, plumbing, and heating work are complete; a lath and/or wallboard inspection before plaster is applied or wallboard joints are taped and finished; any additional inspections required under Section 109 of the International Building Code or the current California Building Code; and a final inspection after finish grading, made once the building is complete and ready for occupancy.

3 lists what that certificate must contain, including the permit number, address, owner, occupancy classification, and design occupant load. 4: a permit that goes 180 days without passing a required inspection is deemed abandoned, and work cannot resume without a new permit, generally at half the original permit fee if the plans are unchanged.

Violations & Fines

Under Section 8.1.02.1(a) (amending CBC Section 103.4), building, altering, or occupying a structure in violation of Title 8 is a misdemeanor, with each day of continued violation a separate offense; the Building Official may issue an administrative citation under Title 1, Chapter 1.7, a court citation, or refer the matter to the City Attorney. Concealing work before a required inspection or occupying without a certificate of occupancy triggers these penalties.

Frequently Asked Questions

What inspections does Clovis require during home construction?
Section 305.5 requires a foundation inspection, a concrete slab or under-floor inspection, a frame inspection, a lath/wallboard inspection, and a final inspection, each triggered at a specific construction stage, before the next phase of work or occupancy can proceed.
Can I pour concrete over the rebar before the City checks it?
No. Section 305.5 says reinforcing steel or structural framework cannot be covered or concealed until the building official has approved it, and the same rule applies to fire-resistive joint and penetration protection.
What happens if I miss a required inspection in Clovis?
Under Section 303.4, going 180 days without a passed inspection is treated as abandonment of the work; the permit becomes void and a new permit, plus fee, is needed to resume construction.
Can I move into my new Clovis home before the final inspection?
Not under Section 309.1 as amended by 8.1.01.1(g); the building cannot be occupied until the building official issues a certificate of occupancy following successful completion of the required inspections.

Sources & Official References

Other rules in Clovis

All Clovis rules

California rules heatmap·Compare Clovis to another location·View the California building safety overview

Get notified when Building Inspections in Clovis, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Inspections in Nearby Cities

How other cities in Fresno County handle building inspections.

Fresno, CA
Some Restrictions