Clovis, CA Building Safety: Building Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified August 2026

Key Facts

Base code adopted
1997 Uniform Administrative Code, local amendments
Building code in force
2025 California Building Code, § 8.1.02
Permit expiration
180 days without starting or continuing work
Plan review fee
65% of building permit fee
Unpermitted-work fee
Equal to permit fee, up to 10x on repeats
Violation penalty
Misdemeanor; each day a separate offense

Summary

Clovis requires a building permit for nearly any construction activity through Municipal Code Section 8.1.01, which adopts the Uniform Administrative Code to regulate the erection, alteration, repair, conversion, demolition, and maintenance of buildings citywide. Local amendments in Section 8.1.01.1 set the permit's 180-day expiration clock, tie fees to City-adopted tables, and escalate an investigation fee for anyone who builds without pulling a permit first.

For the purposes of regulating the erection, construction, enlargement, alteration, repair, moving, removal, conversion, demolition, occupancy, equipment, use, height, area, and maintenance of buildings and structures in the City and providing for the issuance of permits and the collection of fees therefor, the 1997 Edition of the Uniform Administrative Code and Appendices, as prepared by the International Conference of Building Officials, three (3) copies of which have been filed for use and examination by the public in the office of the City Clerk as provided by Sections 50022.1 et seq. of the Government Code of the State, is hereby adopted by reference thereto as if fully set forth in this chapter.

Full Breakdown

1 then amends that adopted code with Clovis-specific rules. 4 if work does not start within 180 days of issuance, or if it is suspended or abandoned for 180 days, and a missed inspection every 180 days also counts as abandonment; restarting after expiration costs a new permit fee, though restarting within a year on unchanged plans costs only half the fee for a new permit. 3: plan review is 65 percent of the building permit fee, 25 percent of the total permit fee for electrical, mechanical, and plumbing work, and 25 percent of the Building Plan Check fee for seismic, disabled access, and energy-efficiency review.

2 charges an investigation fee equal to the permit fee for a first unpermitted-work violation, then a progressively larger fee, three times the permit fee on a second violation by the same permittee, four times on a third, five times on a fourth, up to a ten-times cap, on top of whatever permit fee is ultimately owed. 02 layers the 2025 California Building Code onto this same permitting structure, excluding Chapter 29 (plumbing systems) but including Appendix J (grading).

Violations & Fines

Section 8.1.02.1's amendment to CBC Section 103.4 makes it unlawful, and a misdemeanor, to erect, construct, enlarge, alter, repair, move, remove, convert, demolish, equip, use, occupy, or maintain any building "contrary to or in violation of any of the provisions of this Code," with each day of the violation counted as a separate offense. The Building Official can respond with an administrative citation under Title 1, Chapter 1.7, a Notice to Appear under Title 1, Chapter 1.2, or refer the matter to the City Attorney for legal action, and building without a permit also draws the Section 304.5.2 investigation fee described above.

Frequently Asked Questions

How long is a Clovis building permit valid before it expires?
Section 8.1.01.1's amendment to Section 303.4 gives you 180 days from issuance to start work, and the permit also expires if work is suspended or abandoned for 180 days, including missing a required inspection for 180 days straight. Restarting after expiration on unchanged plans, within a year, costs half of a new permit fee; after a year, or with changed plans, it costs the full fee again.
What does it cost to get a plan reviewed for a Clovis building permit?
The amended Section 304.3 sets the plan review fee at 65 percent of the building permit fee under Table B-1, with electrical, mechanical, and plumbing work reviewed separately at 25 percent of their own permit fees under Tables E-1, M-1, and P-1. Seismic, disabled access, and energy-efficiency review each add another 25 percent of the Building Plan Check fee, charged in addition to the permit fee itself.
What happens if I build in Clovis without pulling a permit first?
Section 8.1.01.1's amendment to Section 304.5.2 charges an investigation fee equal to the permit fee the first time, then escalates for the same permittee: three times the permit fee on a second unpermitted violation, four times on a third, five times on a fourth, and so on up to a ten-times cap, and Section 8.1.02.1 separately makes the underlying construction a misdemeanor.

Sources & Official References

Other rules in Clovis

All Clovis rules

California rules heatmap·Compare Clovis to another location·View the California building safety overview

Get notified when Building Permits in Clovis, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Permits in Nearby Cities

How other cities in Fresno County handle building permits.

Fresno, CA
Some Restrictions