Clovis, CA Building Safety: Plumbing Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified August 2026

Key Facts

Adopted code
2025 CPC, incorporates 2024 UPC
Current amendment
Ord. 25-12, eff. Dec. 31, 2025
Gas reconnection rule
90+ days off requires pressure test, permit
Plan review fee
25% of permit fee, Table P-1
Permit expires
180 days without work commenced
Unpermitted work penalty
Investigation fee up to 10x permit fee

Summary

Clovis enforces the 2025 California Plumbing Code, incorporating the 2024 Uniform Plumbing Code, under Municipal Code Section 8.6.101. A local amendment requires a pressure test and permit before restoring gas service that has been off 90 days or longer at any building in the city.

For the purpose of regulating plumbing systems, the 2025 California Plumbing Code (CPC) promulgated by the California Building Standards Commission, which incorporates the adoption of the 2024 edition of the Uniform Plumbing Code, is hereby adopted by reference thereto as if fully set forth in this Chapter, save and except for portions as are deleted, modified, or amended by the provisions of this Chapter... If any conflicts between this Code and any other City, State, or Federal Code should arise, the most restrictive Code providing the highest level of safety, as determined by the Building Official, shall prevail. ... In all existing commercial and industrial establishments and places of assembly, when the service has been discontinued for ninety (90) days or more, the gas meter may be turned on only after the piping has been pressure tested and when the test and gas appliances have been approved by the Administrative Authority. A permit shall be required for such test.

Full Breakdown

6, most recently amended by Ordinance 25-12, effective December 31, 2025. Copies are kept on file with the City Clerk and Building Official, and any newer edition adopted by the California Building Standards Commission is automatically incorporated. Where the CPC conflicts with any other city, state, or federal code, the Building Official applies whichever provision provides the highest level of safety. 1 for gas service: in existing commercial and industrial establishments and places of assembly where service has been discontinued for 90 days or more, the gas meter may be turned back on only after the piping has been pressure tested and the Administrative Authority has approved both the test and the gas appliances, with a permit required for the test.

The same 90-day pressure-test-and-permit rule applies separately to existing residential buildings. 1(d) sets the plan review fee for plumbing work at 25 percent of the total permit fee shown in Table P-1, charged in addition to the permit fee itself. 1(b) voids a plumbing permit if work has not started within 180 days of issuance or is suspended for 180 days, counting a missed inspection every 180 days as abandonment; reactivating unchanged plans within a year costs half the original permit fee, while any lapse past a year requires a full new fee.

1(f) requires the Building Official to inspect rough plumbing, including under-floor piping and accessories, before it is covered or concealed by concrete or floor sheathing.

Violations & Fines

Restoring gas service without the required pressure test, appliance approval, and permit is enforceable by the Building Official under Section 8.6.102(a). Separately, any plumbing work performed without a permit triggers an investigation fee under Section 8.1.01.1(e) equal to the permit fee on the first offense, rising to three, four, five, and eventually up to ten times the permit fee for repeated unpermitted work by the same party, regardless of whether a permit is later obtained.

Frequently Asked Questions

What plumbing code does Clovis follow?
Section 8.6.101 adopts the 2025 California Plumbing Code, which incorporates the 2024 Uniform Plumbing Code, effective under Ordinance 25-12 as of December 31, 2025. The Building Official applies the most restrictive provision whenever it conflicts with another adopted code.
Do I need a permit to turn my gas back on after it's been shut off?
Yes, if service has been discontinued 90 days or more. Section 8.6.102(a) requires the piping to be pressure tested and the gas appliances approved by the Administrative Authority before the meter is turned on, and a permit is required for that test at both residential and commercial or industrial buildings.
What happens if I do plumbing work without a permit in Clovis?
Section 8.1.01.1(e) charges an investigation fee equal to the permit fee the first time, whether or not a permit is issued afterward. Repeated unpermitted work by the same permittee multiplies the investigation fee up to ten times the standard permit fee.
How long does a Clovis plumbing permit stay valid?
Under Section 8.1.01.1(b), a permit expires if the authorized work is not started within 180 days of issuance or is suspended for 180 days, with a missed inspection every 180 days counting as abandonment. Reviving unchanged plans within a year costs half the original fee.

Sources & Official References

Other rules in Clovis

All Clovis rules

California rules heatmap·Compare Clovis to another location·View the California building safety overview

Get notified when Plumbing Permits in Clovis, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.