Skip to main content
CityRuleLookup

Wayne County, IN Building Safety: Building Inspections (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Inspection notice
At least 24 hours in advance
Required stages
Footing, foundation, under-slab, framing, final
Re-inspection fee
$35
Cover rule
No covering work before inspection approval
Entry authority
Building Commissioner, reasonable times
Penalty
$100 to $1,000 per day

Summary

Wayne County Code § 151.10 requires the Building Commissioner to inspect permitted work at set stages, footing, foundation, under-slab, framing and final, and bars covering any work until it passes inspection, with 24 hours' notice due before each call.

These county ordinances apply to unincorporated areas of Wayne County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

After the issuance of a building permit hereunder, the Building Commissioner shall make, or shall cause to be made, such inspections of the work being done under such permit as are necessary to insure compliance with the provisions of this chapter and the terms of the permit. ... No portion of any work shall be covered or concealed until inspected and approved. ... (1) Footing inspection: performed prior to the placement of concrete. All forms, bulkheads and grade skates must be in place at the time of inspection; ... (5) Final inspection: performed at the time of project completion, prior to using or occupying the structure

Full Breakdown

In unincorporated Wayne County, Indiana, § 151.10(A) makes any person, firm or corporation holding a Building Commissioner permit responsible for requesting inspection of the work whenever required by the chapter or by state statutes, rules or regulations, with the request due at least 24 hours before the inspection is needed. The permit holder must provide access and means for proper inspection, keep the responsible person present on site during the inspection, and never cover or conceal work before it is inspected and approved; the county is not liable for costs of removing or replacing material to allow inspection that was skipped.

Section 151.10(B) sets the required sequence: a footing inspection before concrete placement (forms, bulkheads and grade stakes must be in place); a foundation inspection before backfilling, with drain systems and sump pits complete, and grade or bond beam inspection before their concrete pour; an under-slab inspection before covering underground and under-slab electrical, heating, air conditioning and plumbing systems; a framing inspection before insulation or drywall goes on, with all mechanical, plumbing and electrical work roughed in and masonry firewalls visible; and a final inspection at project completion before the structure is used or occupied.

The Building Commissioner may also order special inspections beyond that list to assure Building Code compliance. Work found incomplete or not ready when an inspector responds triggers the $35 re-inspection fee set in § 151.09, and § 151.11 lets the Commissioner enter any building, structure or premises at reasonable times, on presentation of credentials, to carry out these duties. A certificate of use and occupancy under § 151.13 cannot issue until a final inspection is approved.

Violations & Fines

Covering or concealing work before it is inspected and approved defeats the inspection requirement of § 151.10(A) and exposes the permit holder to the general chapter penalty in § 151.99: a fine of not less than $100 nor more than $1,000, with each day of continuing violation a separate offense, plus possible referral to court if the fine is not paid within ten days. Occupying a structure before the required final inspection and certificate of use and occupancy issue is a separate violation of § 151.13(B), with each day of unlawful occupancy its own offense.

Frequently Asked Questions

How much notice do I need to give for a building inspection in Wayne County?
Section 151.10(A) requires the inspection to be requested at least 24 hours in advance of when it is needed, and the person requesting it must provide access and be present on site during the inspection itself.
What inspection stages does Wayne County require for new construction?
Section 151.10(B) lists footing, foundation (with a separate grade/bond beam check if used), under-slab, framing and final inspections, plus any special inspection the Building Commissioner requires to confirm Building Code compliance.
What happens if the inspector shows up and the work is not ready?
Re-inspection of incomplete or not-ready work is subject to the county's re-inspection fee, set at $35 under the § 151.09 fee schedule, in addition to any delay in scheduling the next inspection.

Sources & Official References

Other rules in Wayne County

All Wayne County rules

Compare Wayne County to another location·View the Indiana building safety overview

Get notified when Building Inspections in Wayne County, IN changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.