New Berlin, WI Building Safety: Plumbing Permits (2026)
Key Facts
- Permit required
- Before any plumbing work starts, §193-4 A
- Exemptions
- Minor faucet repairs and clearing pipe stoppages
- Expiration
- Auto-expires after 60 days of no work
- Late-start penalty
- Double fee for starting before permit issues
- License required
- Plumber must hold state DSPS license, few exceptions
- Governing section
- New Berlin Code of Ordinances § 193-4
Summary
New Berlin requires a permit from the Plumbing Inspector before any plumbing work begins, covering everything from water supply and drainage piping to sewer laterals, though minor faucet repairs and clearing stoppages in soil and waste pipes are exempt from the permit requirement.
A.Required. No work contemplated by this chapter shall be started until a permit therefor has been obtained from the Plumbing Inspector or his authorized agent, provided no permit shall be required for minor repairs to faucets or the removal of stoppages in soil and waste pipes.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Municipal Code: Supplement 3 Update 1).
Full Breakdown
" The permit application must be in writing on Plumbing Inspector forms, identify the property owner and describe the work, and it binds both the owner and the applicant to the chapter's requirements. Once the Inspector is satisfied the proposed work conforms to the chapter and fees are paid, the permit issues and remains valid for continuous performance of that work; it automatically expires if work stops for 60 days without good cause, and automatically expires again when the permitted work is finished, though the Inspector may suspend or revoke it for a violation.
No permit can be issued to an applicant currently in violation of the chapter until the violation is corrected, or to anyone with a pending Plumbing Inspector order, unless the Inspector waives that restriction. Starting work before the permit is issued triggers a double fee under Subsection F. Chapter 193 also adopts Wisconsin's Chapter 145 and the State Plumbing Code, SPS 381 through 387, by reference, and requires that anyone performing plumbing work hold a state license from the Department of Safety and Professional Services, with narrow exceptions for a homeowner working on their own one-family home and for minor repairs. A person aggrieved by a permit refusal, suspension or revocation may seek review under Wisconsin Chapter 68.
Violations & Fines
Violating Chapter 193, including performing plumbing work without a permit or without the required state license, is punishable under the general penalty at Section 1-18 of the Municipal Code per Section 193-6. The Plumbing Inspector may also issue a stop-work order under Section 193-3B(5) for work done in violation of the chapter, and work stopped that way cannot resume without the Inspector's written permission.
Frequently Asked Questions
Do I need a permit to fix a leaking faucet in New Berlin?
How long does a New Berlin plumbing permit stay valid?
What happens if I start plumbing work before getting a permit?
Sources & Official References
Other rules in New Berlin
Compare New Berlin to another location·View the Wisconsin building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Plumbing Permits in Nearby Cities
How other cities in Waukesha County handle plumbing permits.