Stafford Township, NJ Building Safety: Plumbing Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified November 2026

Key Facts

Permit per fixture
$5 for each fixture
Fixture replacement permit
No fee
Commercial or multiple-unit permit
$25 plus $5 for each fixture
Reinspection
$10 each
Permit expiration
No later than one year from issuance
Penalty
$5 to $500 per offense

Summary

Stafford Township regulates plumbing under the Plumbing Code of New Jersey (Revised 1964), adopted by reference in Chapter 230. A permit for new plumbing construction or alteration costs $5 for each fixture, replacing a fixture carries no fee, and every plumbing permit expires no later than one year after issuance.

In connection with the provisions of this chapter and the code hereby established and adopted as a part hereof, the following fees shall be charged and received: ... C. For the filing of plans for proposed plumbing work: $2. D. For the issuance of a permit for proposed plumbing construction or alteration: a fee of $5 for each fixture is hereby established. E. For the issuance of a permit for the replacement of a plumbing fixture: no fee shall be charged. F. For each reinspection of plumbing work caused by the failure of the licensee to comply with the provisions of the code or permit issued: $10. G. For the issuance of a plumbing permit for a commercial building: $25, plus $5 for each fixture. H. For the issuance of a plumbing permit for all multiple units, including condominiums, townhouses and apartments: $25, plus $5 for each fixture.

Full Breakdown

Chapter 230 was adopted by the Board of Health of the Township of Stafford on 5-6-1985 by Ordinance No. 85-3. Section 230-1 establishes a code regulating the installation, maintenance, repair and control of the plumbing of buildings and their connection with outside sewers, cesspools or other receptacles, regulating the practice of plumbing, and regulating the issuance of licenses to practice plumbing, pursuant to P.L. 1950, c. 188 (N.J.S.A. 26:3-69.1 to 3-69.6). Section 230-2 names it the Plumbing Code of New Jersey (Revised 1964), and § 230-3 places three copies on file in the office of the Clerk for public examination.

Section 230-4 prints the fee schedule. Filing plans for proposed plumbing work costs $2. A permit for proposed plumbing construction or alteration costs $5 for each fixture, and a permit for replacing a plumbing fixture carries no fee. A commercial building permit costs $25 plus $5 for each fixture, and a permit for all multiple units, including condominiums, townhouses and apartments, is $25 plus $5 for each fixture. Each reinspection caused by the licensee's failure to comply with the code or permit costs $10. Swimming pool plumbing permits cost $10 above ground and $20 for pools partly or wholly below the surface of the ground.

Licensing fees are in the same section: $100 to examine an applicant for a master plumber license, and $15 for issuing and annually renewing it. Under § 230-6, all fees, penalties and moneys collected go to the Treasurer of the municipality.

Under § 230-7, all permits issued under Chapter 230 expire no later than one year from the date of issuance. Chapter 233 on sewers links plumbing to construction oversight: under § 233-3, every sewer connection must conform to the plumbing subcode of the State Uniform Construction Code and comply with the requirements of the Township's plumbing subcode official.

Violations & Fines

Section 230-5 provides that any person, firm or corporation violating any provision of Chapter 230 or of the Plumbing Code of New Jersey (Revised 1964) shall, upon conviction, pay a penalty of not less than $5 nor more than $500 for each offense. Collected penalties are paid to the municipal Treasurer under § 230-6.

Frequently Asked Questions

How much is a plumbing permit in Stafford Township?
Under § 230-4(D), a permit for proposed plumbing construction or alteration is $5 for each fixture. Commercial buildings and multiple units such as condominiums, townhouses and apartments pay $25 plus $5 for each fixture under items G and H. Filing the plans for proposed plumbing work costs $2.
Do I pay a fee to replace a fixture?
No. Section 230-4(E) says no fee shall be charged for the issuance of a permit for the replacement of a plumbing fixture. The permit is still issued under that item, but there is no charge. Reinspections caused by the licensee's failure to comply cost $10 each under item F.
How long is a Stafford plumbing permit good for?
Section 230-7 provides that all permits issued under Chapter 230 expire no later than one year from the date of issuance. The one-year limit is an outer boundary, so a permit can expire sooner but never later than a year after the date it was issued.
Which plumbing code does Stafford use?
Sections 230-1 and 230-2 adopt by reference the Plumbing Code of New Jersey (Revised 1964), pursuant to N.J.S.A. 26:3-69.1 to 3-69.6. Three copies are kept on file in the Clerk's office for public examination under § 230-3. Violations of that code are punished under § 230-5 by $5 to $500 per offense.

Sources & Official References

Other rules in Stafford Township

All Stafford Township rules

Compare Stafford Township to another location·View the New Jersey building safety overview

Get notified when Plumbing Permits in Stafford Township, NJ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.