Key Facts

R-R lot coverage limit
5% maximum
RL-4 lot coverage limit
50% maximum
Coverage definition
structure area divided by lot area
Applies to
principal and accessory structures combined
Civil penalty
$100 to $1,000 per offense
Enforcing agency
Community Development Department

Summary

In the City of Grand Junction, maximum lot coverage is set district by district under GJMC Chapter 21.03.050: the Residential Rural (R-R) district caps building coverage at just 5% of the lot to preserve its large-lot agricultural character, while the Residential Low 4 (RL-4) district, the city's standard single-unit and duplex zone, allows up to 50% lot coverage.

Residential Rural (R-R). ... Lot Coverage (maximum) Lot coverage 5% ... Residential Low 4 (RL-4). ... Lot Coverage (maximum) Lot Coverage 50%

Full Breakdown

Lot coverage measures how much of a lot's area is occupied by structures: GJMC § 21.14.020 defines it as the percentage of the total lot area covered by structures, calculated by dividing the square footage of structure coverage by the square footage of the lot. Grand Junction sets a separate maximum in the dimensional standards table for each of its residential zone districts under Chapter 21.03.050, rather than one citywide figure.

At the low end, the Residential Rural (R-R) district, reserved for large-lot single-unit dwellings and low-intensity agricultural operations on lots of at least 5 acres, limits lot coverage to just 5% under § 21.03.050(d). At the other end of the residential range, the Residential Low 4 (RL-4) district, applied to typical single-unit and duplex lots as small as 7,000 square feet, allows up to 50% lot coverage under § 21.03.050(h). Denser districts such as Residential Medium and Residential High carry their own maximums listed in the same chapter's dimensional tables, again keyed to the applicable zone district.

Lot coverage is calculated for the whole parcel and applies to principal and accessory structures alike, so a detached garage, shed or accessory dwelling unit counts against the same percentage cap as the house itself. A property owner proposing a project that would exceed the applicable percentage must either redesign the structure or pursue the dimensional adjustment procedures in Chapter 21.03.040, administered by the Community Development Department.

Violations & Fines

Community Development enforces lot coverage as a zoning dimensional standard under GJMC § 21.13.030. A structure built or expanded beyond its district's lot coverage maximum is an unlawful development, and under § 21.13.050(c) the owner faces a civil penalty of $100 to $1,000 per offense, with each day of a continuing violation a separate offense up to a $10,000 cap. Section 21.13.060 makes a knowing violation a misdemeanor carrying up to a $1,000 fine or one year in jail.

Frequently Asked Questions

What is the maximum lot coverage allowed in Grand Junction?
Grand Junction sets lot coverage limits district by district in GJMC Chapter 21.03.050 rather than as one citywide number. The Residential Rural (R-R) district caps coverage at 5% of the lot under § 21.03.050(d), while the Residential Low 4 (RL-4) district, used for most single-unit and duplex lots, allows up to 50% under § 21.03.050(h).
How is lot coverage calculated?
GJMC § 21.14.020 defines lot coverage as the percentage of the total lot area covered by structures, calculated by dividing the square footage of structure coverage by the square footage of the lot. The calculation includes both the principal building and any accessory structures such as garages, sheds or accessory dwelling units on the same parcel.
Does a detached garage count toward the lot coverage limit?
Yes. Lot coverage is measured against the whole parcel and covers principal and accessory structures alike, so a detached garage, shed, carport or accessory dwelling unit adds to the same percentage cap as the main house under the applicable district's dimensional standards table in GJMC Chapter 21.03.050.
What happens if a project exceeds the lot coverage maximum?
The Community Development Department can require the project be redesigned or refer the case for a civil penalty under § 21.13.050(c) of $100 to $1,000 per offense, capped at $10,000 for continuing violations, and a knowing violation is a misdemeanor under § 21.13.060 punishable by up to a $1,000 fine or a year in jail.

Sources & Official References

Other rules in Grand Junction

All Grand Junction rules

Compare Grand Junction to another location·View the Colorado building setbacks & zoning overview

Get notified when Lot Coverage Limits in Grand Junction, CO changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.