Stormwater Management

Brick Township requires stormwater management measures for major development disturbing one or more acres of land, mandating green infrastructure, groundwater recharge, and runoff quality and quantity controls under Chapter 396.

Brick Township Stormwater Management Standards

Some Restrictions

Brick Township Code § 396-3

This chapter shall be applicable to the following major developments: Nonresidential major developments; and Aspects of residential major developments that are not preempted by the Residential Site Improvement Standards at N.J.A.C. 5:21. This chapter shall also be applicable to all major developments undertaken by the Township of Brick, the Brick Housing Authority, the Brick Municipal Utilities...

Erosion Control

Before any grading, excavation, or fill work, Brick Township requires an engineer-sealed site plan under Chapter 383 that delineates erosion control measures and commits to Soil Conservation District compliance until the disturbed soil is stabilized.

Brick Township Soil Erosion Control Permit

Some Restrictions

Brick Township Code § 383-4B(12)

Measures for the prevention of soil erosion and sediment control during construction until soil is stabilized. The applicant shall comply with all local Soil Conservation District requirements. (13) Methods of final soil stabilization and description of ground cover, plantings, vegetation, and landscaping. Residential properties shall receive a minimum of four inches of topsoil on all distur...

Flood Zones

Brick Township requires a development permit before any construction, fill, or land alteration in FEMA-mapped special flood hazard areas, with elevation and floodproofing certification and Municipal Engineer review of every application.

Brick Township Flood Zone Development Permits

Some Restrictions

Brick Township Code § 196-12

A development permit shall be obtained before construction or development begins, including placement of manufactured homes, within any area of special flood hazard established in § 196-7. Application for a development permit shall be made on forms furnished by the Municipal Engineer and may include, but not be limited to; plans in duplicate drawn to scale showing the nature, location, dimensio...

Boat Dock Permits

Brick Township requires a Township Engineer permit before building any dock, pier, boat lift, or bulkhead, plus a separate zoning use permit and NJDEP waterfront approval.

Brick Township Boat Dock Permits

Significant Restrictions

Brick Township Code § 168-4A(2)

Construct a boat basin, boat docking facility, bulkhead, dock, pier, boat lift, or other water use structure, in whole or in part, unless and until an engineering permit is obtained for such construction from this municipality, through its Township Engineer...

Flood Elevation Requirements

Brick Township requires new and substantially improved homes in flood hazard areas to sit one foot above the base flood elevation, not just at it.

Brick Township Flood Elevation Freeboard

Some Restrictions

Brick Township Code § 196-18

New construction and substantial improvement of any residential structure, including manufactured homes, shall have the lowest floor, including basement together with the attendant utilities and sanitary facilities, elevated above the base flood elevation or best available flood hazard data, whichever is the more restrictive standard, in compliance with applicable construction codes plus one fo...