Key Facts

Governing section
§ 22-3(a)(14), Ord. 2024-11013
Generator maintenance/testing barred
7:00 p.m. to 7:59 a.m.
Data-center generators
Not "residential mechanical devices"
Residential HVAC cap, § 22-3(a)(11)
85 dBA
Enforcement
Irving police / code enforcement

Summary

Irving's noise code singles out standby generators at data centers: they cannot be tested or run for maintenance between 7:00 p.m. and 7:59 a.m., and are expressly excluded from the 85 dBA allowance that covers residential mechanical equipment.

(14) Standby power generators. Generators must be installed and operated only in accordance with manufacturer's specifications and in accordance with permitting standards and approvals as established by the city's inspection department. Additionally, for the purposes of this code, standby generators (including those at data centers or other commercial/industrial properties) are not considered "residential mechanical devices" and may not be tested or operated for maintenance between the hours of 7:00 p.m. and 7:59 a.m.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4988517; v32 updated 2026-07-30).

Full Breakdown

Irving City Code § 22-3(a)(14) names data centers directly. Standby generators must be installed and operated only in accordance with the manufacturer's specifications and under permitting standards and approvals set by the city's Inspections Department. The code states that standby generators "including those at data centers or other commercial/industrial properties" are not "residential mechanical devices," so the 85 dBA cap in subsection (a)(11) that covers HVAC, refrigeration, and ventilation equipment does not apply to them. Those generators may not be tested or operated for maintenance between 7:00 p.m. and 7:59 a.m. Chapter 22 is enforced by Irving police and code enforcement officers.

Violations & Fines

Testing or running a data-center standby generator for maintenance between 7:00 p.m. and 7:59 a.m., or operating one outside manufacturer specifications or without required Inspections Department approval, is a per se violation of the noise chapter.

Frequently Asked Questions

Does Irving set a fixed decibel cap for data-center noise?
No single dBA number targets data centers. The 85 dBA limit in § 22-3(a)(11) applies to residential mechanical devices, and § 22-3(a)(14) expressly excludes data-center standby generators from that category.
When can a data center run its backup generator?
Standby generators must be installed and run per manufacturer specifications with Inspections Department approval, and they cannot be tested or operated for maintenance between 7:00 p.m. and 7:59 a.m.

Sources & Official References

Other rules in Irving

All Irving rules

Texas rules heatmap·Compare Irving to another location·View the Texas data centers & crypto mining overview

Get notified when Data Center Noise Limits in Irving, TX changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Data Center Noise Limits in Nearby Cities

How other cities in Dallas County handle data center noise limits.

Dallas, TX
Light Restrictions