Key Facts

Dedicated ordinance
Yes - O2M26-4863
Status
Prohibited in all zones
Adopted
June 22, 2026
Employment zones
PO and I: not allowed
Permit path
None available

Summary

Alhambra prohibits data centers citywide. Ordinance O2M26-4863, adopted June 22, 2026, created a Data Centers use classification and marked it "not allowed" in both employment zones, PO and I. No other zone lists the use, so it is barred everywhere.

Data Centers. Facilities used primarily for analyzing, processing, storing, converting, transmitting, distributing, and managing electronic data for on-site or off-site use. These facilities typically house computer, network, and telecommunication equipment, systems, servers, appliances, and other associated components related to electronic data operations.

Source: Alhambra Municipal Code Title 23 (Zoning) & Title 18 (Community Noise and Vibration Control)View official code

Full Breakdown

Table 23.06.020 of the Alhambra Zoning Code governs the two Employment Zoning Districts: PO (Professional Office) and I (Industrial). Under Ordinance O2M26-4863, effective August 1, 2026, the Data Centers row carries a dash in both PO and I, which the table legend defines as "use not allowed." Section 23.06.020 states that land uses not listed in the table and not substantially similar to listed uses are prohibited, and no residential, commercial, or public/semi-public table lists data centers. The result is a citywide prohibition with no conditional use permit path. The City found the amendment exempt from CEQA. Alhambra follows neighboring Monterey Park rather than Los Angeles County, which allows data centers in industrial zones.

Violations & Fines

Establishing or operating a data center in Alhambra is a zoning violation. Community Development enforces Title 23 through permit denial, stop-work orders, administrative citations, and abatement of the unlawful use.

Frequently Asked Questions

Can a data center be built in Alhambra?
No. Ordinance O2M26-4863 lists Data Centers as "not allowed" in the PO and I employment zones, and no other zone permits the use. Section 23.06.020 prohibits uses that are not listed.
What counts as a data center under Alhambra's code?
Chapter 23.43 defines it as a facility used primarily for analyzing, processing, storing, converting, transmitting, distributing, and managing electronic data. Server rooms incidental to another primary use on the same site are excluded.
Who do I contact about Alhambra's data center rules?
The Planning Division at 111 South First Street, 626-570-5007. The City Council and Planning Commission hold public hearings on zoning text amendments, and the Council placed the ban on the November 2026 ballot.

Sources & Official References

Other rules in Alhambra

All Alhambra rules

California rules heatmap·Compare Alhambra to another location·View the California data centers & crypto mining overview

Get notified when Data Center Zoning & Siting in Alhambra, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Data Center Zoning & Siting in Nearby Cities

How other cities in Los Angeles County handle data center zoning & siting.

Long Beach, CA
Light Restrictions
Los Angeles, CA
Some Restrictions
El Monte, CA
Some Restrictions
Pasadena, CA
Some Restrictions
Torrance, CA
Some Restrictions
Palmdale, CA
Some Restrictions
Lakewood, CA
Some Restrictions
Norwalk, CA
Some Restrictions