Gaithersburg, MD Data Centers & Crypto Mining: Data Center Zoning & Siting (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Allowed zones
I-1 Light Industrial, I-3 Industrial Office Park only
Permission type
Conditional use, not by-right
Prohibited zones
CB, C-1, C-2, E-1/E-2, all residential/floating zones
Governing table
Table 24-3.10-1, Sec. 24-3.10
Enforcement
Municipal infraction, up to $1,000 added fine

Summary

Gaithersburg allows data centers and cryptocurrency-mining facilities only as a conditional use in the I-1 Light Industrial and I-3 Industrial Office Park zones. Table 24-3.10-1 of the city's own zoning code, adopted because Gaithersburg (unlike most Montgomery County municipalities) runs independent zoning, marks the use with a flat dash, meaning prohibited, in every commercial, employment, residential and floating district.

● = Permitted by-right ◑ = Conditional use Ⓢ = Special Exception

- = Prohibited ... Use Use-Specific Standards CB C-1 C-2 I-1 I-3 E-1 & E-2 ... Data center or data/crypto currency mining - - - ◑ ◑ -

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 52 Update 1).

Full Breakdown

The City of Gaithersburg is one of only two municipalities in Montgomery County, along with Rockville, that exercises its own independent planning and zoning authority rather than deferring to the county's charter zoning code. Its Chapter 24 zoning ordinance, adopted by Ordinance No. O-5-24 on July 15, 2024, governs data centers directly. 10-1, the Non-Residential Zoning Districts Comprehensive Principal Use Permissions Table, lists 'Data center or data/crypto currency mining' as a conditional use, marked with the conditional-use symbol, in only two of the city's six standard non-residential zones: I-1 Light Industrial and I-3 Industrial Office Park.

The same row carries a dash in the CB Commercial Buffer, C-1 Local Commercial, C-2 General Commercial and combined E-1/E-2 Urban Employment columns, meaning the use is prohibited outright there. 1-1, the residential-district permissions table, or on the floating-zone table covering the CBD Central Business District, CD Corridor Development, MCD Mixed-Commercial Development and MXD Mixed-Use Development zones, both of which list a flat dash for the same use, so it is barred from every residential and floating zone in the city as well. 4, defines a data center or data/cryptocurrency mining facility as a physical location that stores computing machines and their related hardware equipment, and that either stores a company's digital data or provides the mining function for cryptocurrency, so a crypto-mining warehouse is treated identically to a conventional server farm for siting purposes.

Because the use is conditional, not by-right, even inside I-1 or I-3 an operator must secure conditional-use approval, which under Chapter 24's site-plan articles typically requires a site development plan reviewed by the planning division and planning commission before a building permit can issue. A prospective operator should confirm a parcel's zoning designation on the official city zoning map before committing to a site, since neither Montgomery County zoning nor a neighboring municipality's rules apply inside Gaithersburg's limits.

Violations & Fines

Siting or operating a data center outside the I-1 or I-3 zones, or without conditional-use approval inside them, is a zoning violation under section 24-15.1 and is enforced as a municipal infraction under chapter 1, section 1-9. Planning and Code Administration investigates complaints, and the city manager may order discontinuance of the illegal use. Fines run up to the maximum set by city council resolution, with an added penalty of up to $1,000 for late payment, and section 1-11 allows the city to lien the property for correction costs.

Frequently Asked Questions

Can I build a data center anywhere in Gaithersburg?
No. Table 24-3.10-1 of the zoning code permits a data center or crypto-mining facility only as a conditional use in the I-1 Light Industrial and I-3 Industrial Office Park zones. It is prohibited in the CB, C-1, C-2, and combined E-1/E-2 Urban Employment zones, and it does not appear as an allowed use in any residential or floating zone, so it cannot locate there either.
Does Montgomery County zoning control where a data center can go?
No. Gaithersburg is one of the few Montgomery County municipalities that runs its own independent zoning system rather than being zoned by the county, so the city's Chapter 24, not the county charter zoning code, controls siting decisions inside Gaithersburg's limits.
Is a crypto-mining operation treated differently than a data center?
No. Chapter 24's definitions article defines 'data center or data/cryptocurrency mining' as a single use covering any facility that stores computing hardware for digital data storage or that executes cryptocurrency mining functions, so both are subject to the identical I-1/I-3 conditional-use rule.
What happens if a data center opens in a prohibited zone?
The city treats it as a zoning violation enforceable as a municipal infraction under section 24-15.1 and chapter 1, section 1-9. The city manager can order the use discontinued, fines can reach the council-set maximum plus a late penalty of up to $1,000, and section 1-11 lets the city place a lien on the property for correction costs.

Sources & Official References

Other rules in Gaithersburg

All Gaithersburg rules

Compare Gaithersburg to another location·View the Maryland data centers & crypto mining overview

Get notified when Data Center Zoning & Siting in Gaithersburg, MD changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.